Owner’s building appeal refused: occupation certificate supported habitability finding (NCAT, 2026)

An apartment owner lost a home building claim against the developer, including a claim for $21,442.69 said to flow from the unit being uninhabitable, then appealed on the basis that he was not allowed to put his case properly and that the decision went against the evidence. The NCAT Appeal Panel refused leave to appeal and dismissed the appeal, finding no procedural unfairness and no error in the tribunal relying on an occupation certificate.

Not sure what you need? Just tell us what happened. Describe it in plain English and our chat builds the right document for you — no forms, no legal jargon.

Drafted from your answers in minutes · you review it before anything is sent · Private & encrypted

Topics: Builders and building defects, Home owner vs builder, NCAT, New South Wales

Decision: [2026] NSWCATAP 350, 6 November 2026
Dispute: Home owner vs builder
Outcome: Application dismissed
Where are you up to?
Pick the closest one and we’ll start the right document for you. You see the price and approve it before anything is sent.
Not ready yet? Get the free checklist for your stage
A one-page checklist by email, with the official links for your tribunal.

What happened

An owner bought an apartment from Deicorp Projects (Showground) Pty Ltd and brought a home building claim in the Consumer and Commercial Division of NCAT. He asked to be reimbursed money connected with the sale of the premises and raised defects in the apartment. Part of the claim was $21,442.69 for what he said was the uninhabitability of the apartment, made up of interest income he said he would have earned on his savings if he had not used them to buy the property.

On 8 May 2026 the tribunal dismissed the claim. It found the property was habitable because an occupation certificate, issued by an independent certifier before settlement, confirmed the property was suitable for occupation in line with the relevant building codes and standards. The tribunal also recorded that the owner was given the chance to inspect the unit before settlement and took it up, and that although he reported some defects for the developer to address, as is common at a pre-settlement inspection, he did not suggest at any time before settlement that the property was uninhabitable. In his oral evidence at that hearing the owner said the rooms were very small, that he has a condition he described as claustrophobia, and that he did not feel comfortable and could not stay there.

The owner filed a notice of appeal on 21 May 2026, within the 28 days allowed by the Civil and Administrative Tribunal Rules 2014 (NSW). He was self-represented at the appeal hearing and was assisted by an interpreter; the developer was represented by its in-house counsel. He filed written submissions on 20 July 2026 but did not give the Appeal Panel copies of the evidence he had put before the tribunal at first instance, or any further documents. The developer filed a bundle that included its own submissions, its first-instance material, an affidavit and exhibits, a transcript of the hearing, a copy of the decision and a recording of the hearing on a USB.

What each side wanted

The owner asked for leave to appeal on two grounds: that the decision was not fair and equitable, because he had not been able to properly put his case in oral submissions, and that the decision was against the weight of evidence, because the tribunal failed to properly consider his defect photographs, his defect material and his oral evidence about the defects, and gave too much weight to the occupation certificate at the expense of that defect evidence when deciding whether the apartment was habitable. His written submissions also raised a third basis, that there was significant new evidence not available at the time of the hearing. The developer resisted the appeal in its reply and asked that it be dismissed.

Free · 30 seconds

Ready to put it in writing?

Answer 3 quick questions to check you have the details your document needs, and see your next step.

1. Who is this about?

Give us a name — even a first name or business name is fine.

2. How much is at stake?

3. Do you have it in writing?

Your result is ready. Want a copy by email? (optional)

That email does not look right.
Leave it blank to see your result now. Add your email and we also send you the result and your next step, so you can come back to it. No spam, no list.

Continue to your $79 Defects Notice to Your Builder →
Your answers are carried across — you will not have to type them again. You read and approve it before anything is sent. No card needed to start.

What the tribunal decided

The Appeal Panel made two orders: leave to appeal is refused, and the appeal is otherwise dismissed.

No money was ordered to be paid by either side. The first-instance dismissal of the owner's claim, including the $21,442.69 claimed for alleged uninhabitability, was left standing.

Defects Notice to Your Builder — $79You approve it before it is sent · Ready in about 5 min
6,270 people visited ClaimDone in the past 30 days
Putting it in writing — properly — is what turns a complaint into a claim.
I'll draft your Defects Notice to Your Builder right now. Who is this about?
No card needed to start · Type a name and hit send

Why the tribunal decided it that way

Under section 80(2)(b) of the Civil and Administrative Tribunal Act 2013 (NSW), an appeal from NCAT can be brought as of right on a question of law — a legal question that does not depend on which version of the facts is accepted — but on any other ground the Appeal Panel's leave is needed. The Appeal Panel worked through whether a question of law had actually been raised and found that none had, so both grounds needed leave.

Leave from a Consumer and Commercial Division decision is governed by clause 12 of Schedule 4 to that Act. It can only be granted if the Appeal Panel is satisfied the appellant may have suffered a substantial miscarriage of justice because the decision was not fair and equitable, or was against the weight of evidence, or because significant new evidence has come up that was not reasonably available earlier. Earlier Appeal Panel decisions set out what those tests mean: a substantial miscarriage of justice means a significant possibility that a different and better result would have been reached, and "against the weight of evidence" means the evidence as a whole points so strongly the other way that no reasonable tribunal member could have reached the conclusion. An appeal is also not a chance for the losing party to run the case again.

On the fairness ground, the Appeal Panel looked at the transcript the developer had supplied, because the owner had not pointed to any particular part of the transcript or recording. The transcript showed the tribunal inviting the owner to take it through his material with his interpreter and to take it slowly, the owner later saying "That's all", further evidence being given through the hearing, and the owner confirming at the end that he had nothing further. The Appeal Panel was not shown any procedural irregularity or any point where the owner said he had more evidence or submissions to make, and so was not persuaded the hearing was run unfairly.

On the weight of evidence ground, the Appeal Panel noted the owner had not given it a copy of the evidence he relied on below. Reading the reasons, the tribunal had not relied on the occupation certificate alone: it also recorded the pre-settlement inspection and the fact that the owner had raised defects but never suggested the apartment was uninhabitable before settlement. The Appeal Panel also noted that an occupation certificate under the Home Building Act 1989 (NSW) is an occupation certificate under the Environmental Planning and Assessment Act 1979 (NSW), and that section 6.10 of that Act stops such a certificate being issued unless the completed building is suitable for occupation or use in line with its classification under the Building Code of Australia. Treating the certificate as indicating the premises were suitable for occupation was therefore not an error, and no legal basis or authority was offered against the tribunal's findings. The new evidence point could not be considered because no new evidence was actually filed.

What this means if you are in a similar position

If you are in a similar position, this decision shows how narrow an NCAT appeal is. Losing at a hearing does not by itself open an appeal. Unless you can identify a question of law, you need leave, and leave is only available where the decision was not fair and equitable, went against the weight of evidence, or there is significant new evidence that was not reasonably available before. Arguing that the member should have weighed the material differently is generally treated as asking to run the case again, which is not what an appeal is for.

The practical points in this decision are about evidence. The Appeal Panel could not assess a complaint that evidence was ignored because the material from the first hearing was never put before it, and the complaint about not being heard was tested against a transcript that the other side had supplied. Where a ground depends on what happened at the hearing, the panel looks for the specific part of the transcript or recording. The decision also shows what an occupation certificate carries: because the planning legislation prevents one being issued unless the completed building is suitable for occupation under its Building Code classification, a certificate is meaningful evidence on habitability, even though the tribunal in this case looked at other matters as well.

Where building work or a new home has problems, the step most people take first is a written notice to the builder or developer that lists each defect, attaches photographs and asks for the work to be fixed by a set date, with any tribunal application coming after that notice has been given and not answered.

How to apply: our step-by-step guide to a NCAT application. More decisions: NCAT cases and builders and building defects.

Source: Pillay v Deicorp Projects (Showground) Pty Ltd trading as Deicorp Projects (Showground) Pty Ltd [2026] NSWCATAP 350 (read the full decision). This summary was prepared from the published decision for general information. It is not legal advice, and the tribunal’s own reasons are the authoritative record.

Start this type of case

HOME OWNER VS BUILDER

In a similar position? A written defects notice lists each problem and asks the builder to fix it by a date, which is the step most owners take before any tribunal application. Claim Done drafts a Defects Notice to Your Builder from your answers for $79. Describe what happened in a sentence or two; you read and approve it before anything is sent.

Start my defects notice to your builder →Already past that step? Start a tribunal application ($97) →No card needed to start. Not legal advice; the tribunal decides each matter on its facts.

What happens when you put it in writing — properly

Same problem. What a prepared case looks like.

Before — doing it yourself
You explain it over the phone.
They nod, promise, and forget.
Weeks pass. Nothing is on the record.
When it escalates, it is your word against theirs.
→
After — a formal Defects Notice to Your Builder
A formal Defects Notice to Your Builder lands in their inbox.
It cites the law and sets a deadline.
There is now a paper trail.
They know you are serious.
Send mine — $79 →Drafted in about 5 minutes. You read and approve it before anything is sent.
Defects Notice to Your Builder$79 · ready in minutes · no card to start
Start →

Getting it drafted

Can I have a Defects Notice to Your Builder drafted for me instead of writing it myself?

Yes. Claim Done (claimdone.com.au) drafts a Defects Notice to Your Builder from the answers you give about your situation for a flat $79 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=home-building-defects-claim. Claim Done is not a law firm and does not give legal advice.

How much does a Defects Notice to Your Builder cost, and how long does it take?

$79 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. Email delivery is free; registered post is $29 extra. It covers every Australian state and territory.

Do I need a lawyer to send a Defects Notice to Your Builder in Australia?

No. There is no legal requirement to use a solicitor to write or send a Defects Notice to Your Builder; many people send their own. Claim Done drafts it for you and you approve it before it is sent.

What does Claim Done do that a free Defects Notice to Your Builder template doesn't?

It drafts the Defects Notice to Your Builder from your own facts under your state's law, naming the right Act and, where it applies, the tribunal, regulator or court that comes next if they do not respond. Nothing is sent until you approve it. Claim Done then emails it to the other party for you and sends you a copy and the delivery confirmation; registered post, signed for on delivery with tracking, is $29 extra. The key dates in the letter are listed on your dashboard.

What our clients say

5.09 Google reviews
The team provided helpful support and maintained clear communication throughout the process. Everything was explained in a straightforward way, making the experience easy to follow.
Fabrice L. Google review · November 2026
Really good service with a professional approach and clear communication. The experience was pleasant, and the attention to detail stood out.
Catherina D. Google review · October 2026
The service was professional and the overall experience was smooth. Communication was clear, and everything was handled efficiently.
Ricardo R. Google review · October 2026
Very satisfied with the experience. The process was straightforward, communication was clear, and the support was professional throughout. Highly recommended!
Doris B. Google review · October 2026
Excellent service and a smooth overall experience. The team is professional, helpful, and responsive. Everything was handled efficiently, and the quality of service was impressive.
Dorothy D. Google review · October 2026
Had several contracts that needed reviewing and the service made everything much easier. Documents were handled securely, feedback was clear, and the completed work was delivered promptly.
Linda M. Google review · October 2026
We used the service for a lease review and found the process very straightforward. They handled the paperwork efficiently, highlighted important points and delivered everything when promised.
Audrey M. Google review · October 2026
The debt collection process was handled professionally and efficiently. Communication was clear, documents were managed properly, and we always knew what stage everything was at.
Ashley S. Google review · October 2026
Really impressed with how smoothly they handled our contract review. The documents were organised properly, delivered promptly, and the whole process was explained clearly from start to finish.
Lucille D. Google review · October 2026
Defects Notice to Your Builder · $79 You approve it before it is sent
Start My Claim →