If a builder has issued a variation or progress claim that you believe is wrong, inflated or unauthorised, the Tasmanian Civil and Administrative Tribunal (TASCAT) is the body that can resolve the dispute without you needing to go to court. TASCAT handles a wide range of building and construction matters between homeowners and licensed builders in Tasmania, and its processes are designed to be accessible to people without legal training.
How TASCAT Decides a Variation or Progress Claim Dispute
When TASCAT examines a dispute about a builder’s variation or a progress claim, it focuses on what was actually agreed between the parties. The tribunal will look at:
- The written building contract and any annexures or schedules attached to it
- Whether the variation was properly authorised in writing before the work was carried out, as required under Tasmanian home building law
- Whether the amount claimed reflects the work genuinely completed at the relevant stage
- Any written communications — emails, letters, text messages — that show what was agreed or disputed at the time
- Industry standards and, where relevant, expert evidence about the value or quality of the work
TASCAT can hear evidence from both sides and may inspect the property or appoint a building expert to assist it. The tribunal applies the law impartially, so simply disputing a figure is not enough — you need to show why the claim is not supported by the contract or by the work actually done.
Orders TASCAT Can Make
TASCAT has broad powers to resolve building payment disputes. Depending on the evidence and the law, the tribunal may order that:
- A variation or progress claim is reduced to reflect the work actually completed
- An unauthorised variation is not payable at all
- Money already paid in excess is refunded to the homeowner
- Disputed amounts are withheld until defective or incomplete work is rectified
- The contract is interpreted in a particular way going forward
The tribunal aims for practical outcomes. It cannot award unlimited damages, and its jurisdiction has monetary limits set by Tasmanian legislation — check the TASCAT website for the current figures that apply to your type of dispute.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who did the work?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
How to Apply to TASCAT
Before applying, you should attempt to resolve the dispute directly with your builder in writing. If that fails, the general process for lodging a matter at TASCAT is:
- Download the correct application form from the TASCAT website — forms differ depending on whether your dispute falls under the building and construction stream
- Complete the form clearly, setting out the amount in dispute and the reasons you believe the claim is wrong
- Pay the applicable filing fee — current fees are listed on the TASCAT website and vary by claim size
- Serve a copy of your application on the builder as directed by the tribunal’s rules
- Attend any preliminary conference or hearing that TASCAT schedules
TASCAT staff can explain the process but cannot give you legal advice. For specific procedural questions, always refer to the official TASCAT website or seek independent legal help.
Evidence That Helps Your Case
Strong evidence is the foundation of a successful TASCAT application. Gather and organise:
- Your signed building contract, including any variation clauses
- All written variation requests and approvals — or evidence that no approval was given
- Progress payment schedules from the contract, compared to the claims actually issued
- Photographs of the work at the relevant stages
- Invoices, receipts or independent quotes showing what the work should have cost
- A builder’s inspection report or quantity surveyor’s assessment if the amounts are large
- All correspondence with the builder, including text messages and emails
How Claim Done Helps
A clearly drafted dispute letter or formal response to a progress claim puts your position on the record before you ever set foot in TASCAT. Claim Done prepares the right document for your situation — whether that is a written objection to an unauthorised variation, a formal dispute notice challenging an inflated progress claim, or a letter preserving your rights under the contract. Having a professionally worded document strengthens your credibility with the tribunal and shows you followed the correct process from the start.
What happens when you put the builder on formal notice
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Dispute a Builder's Variation, Overcharge or Progress Claim drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Dispute a Builder's Variation, Overcharge or Progress Claim from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=builder-variation-dispute. Claim Done is not a law firm and does not give legal advice.
How much does a Dispute a Builder's Variation, Overcharge or Progress Claim cost, and how long does it take?
$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.
Do I need a lawyer to send a Dispute a Builder's Variation, Overcharge or Progress Claim in Australia?
No. There is no legal requirement to use a solicitor to write or send a Dispute a Builder's Variation, Overcharge or Progress Claim; many people send their own. Claim Done drafts it for you and you approve it before it is sent.