If you are a Western Australian homeowner who believes your builder has charged for an unauthorised variation, inflated a progress claim, or demanded payment you do not owe, the State Administrative Tribunal (SAT) is the body that can hear and resolve your dispute. SAT has specialist jurisdiction over residential building disputes in WA, making it the appropriate forum when negotiations with your builder have broken down.
How SAT Decides a Building Variation or Progress Claim Dispute
SAT examines these disputes by looking at the terms of your building contract, the work that was actually carried out, and whether the correct processes for authorising variations were followed. In Western Australia, residential building contracts are regulated and must meet certain standards — variations generally need to be agreed in writing before work begins. When assessing a claim, SAT will consider:
- Whether the variation was properly authorised by you in writing before the builder proceeded
- Whether the amount claimed matches the agreed or reasonable cost of the work described
- Whether each progress claim corresponds to a stage of work that has genuinely been completed
- The conduct of both parties throughout the project, including any written communications
- Expert or independent assessments of the work and its value where relevant
Orders SAT Can Make
SAT has broad powers to resolve building payment disputes. Depending on the circumstances, the tribunal may order that:
- A disputed variation charge be reduced or set aside entirely
- A progress payment be adjusted to reflect the work actually completed
- Money already paid be refunded to the homeowner
- A specific amount be paid by one party to the other
- The parties follow a particular course of action to resolve outstanding issues
SAT may also require the parties to attend mediation or a conciliation conference before a formal hearing, which often helps settle disputes faster and at lower cost.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who did the work?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
How to Apply to SAT
Before applying, it is worth writing formally to your builder setting out your objection and giving them an opportunity to respond — this paper trail will assist your case. When you are ready to proceed, the application is made directly to SAT using the forms published on the SAT website. Current application fees and the correct forms for building disputes are listed on the SAT website and may change from time to time, so always check there for up-to-date information. Once your application is lodged, SAT will notify the builder and set the matter down for a preliminary conference or hearing. You will need to serve your documents on the other party in accordance with SAT’s requirements.
Evidence That Helps Your Case
Strong, well-organised evidence significantly improves your chances of a successful outcome. The most useful material includes:
- Your signed building contract and any written variation approvals (or proof that none exist)
- All invoices, payment claims and receipts exchanged with the builder
- Photographs of the work at relevant stages, clearly dated
- Written communications — emails, text messages and letters — especially any where the builder asked for approval or you raised concerns
- An independent building inspection report or quantity surveyor’s assessment if the dispute involves the value or quality of work
- A clear written summary of the timeline of events and the amounts in dispute
How Claim Done Helps
The right document can make a significant difference before you ever set foot in a tribunal. Claim Done prepares a formally worded letter of dispute addressed to your builder that clearly sets out your legal position, identifies the variation or payment claim you are challenging, and demands a response within a specified timeframe. A professional dispute letter demonstrates that you are serious, creates a written record for SAT, and often prompts builders to negotiate without the need for a full hearing. Having this document ready also shows SAT that you attempted to resolve the matter before applying.
What happens when you put the builder on formal notice
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Dispute a Builder's Variation, Overcharge or Progress Claim drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Dispute a Builder's Variation, Overcharge or Progress Claim from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=builder-variation-dispute. Claim Done is not a law firm and does not give legal advice.
How much does a Dispute a Builder's Variation, Overcharge or Progress Claim cost, and how long does it take?
$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.
Do I need a lawyer to send a Dispute a Builder's Variation, Overcharge or Progress Claim in Australia?
No. There is no legal requirement to use a solicitor to write or send a Dispute a Builder's Variation, Overcharge or Progress Claim; many people send their own. Claim Done drafts it for you and you approve it before it is sent.