If a builder has charged you for a variation you never agreed to, or issued a progress claim that seems inflated or premature, the ACT Civil and Administrative Tribunal (ACAT) is the main forum where ACT homeowners can resolve those disputes without going to court. ACAT handles a wide range of building and construction matters, including disagreements about variation costs, overcharges and the validity of progress claims under residential building contracts.
How ACAT decides a variation or progress claim dispute
When ACAT examines a disputed variation or progress claim, it looks at whether the original building contract authorised the variation and whether the correct process was followed to create a binding variation agreement. Key questions the tribunal considers include:
- Was the variation requested or approved in writing, as most residential building contracts in the ACT require?
- Was the price or method of calculating the variation cost clearly agreed before the work was done?
- Does the builder’s progress claim accurately reflect the stage of work actually completed at the time the claim was made?
- Are the amounts charged consistent with the contract, any approved variations and the reasonable cost of the work?
ACAT will read the contract, any written variations, correspondence between the parties and any expert evidence about the value or quality of work. The tribunal applies ACT building legislation and general contract principles to reach its decision.
Orders the tribunal can make
ACAT has broad powers to resolve building payment disputes. Where a homeowner succeeds, the tribunal may order:
- that a disputed amount is not payable, or that the contract price be reduced to reflect what was actually agreed
- repayment of amounts already paid that the tribunal finds were not properly owed
- that the builder complete specified work before further payment falls due
- that a building expert be appointed to assess disputed work or costs
- monetary compensation where loss flows from an unjustified or defective variation
ACAT can also make orders about the future conduct of the building contract, which can be particularly useful when the project is still underway.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who did the work?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
How to apply to ACAT
Applications are made directly to ACAT. The general process involves completing the relevant application form, paying the applicable filing fee and serving a copy of your application on the builder. Current forms, fee schedules and guidance on how to serve documents are published on the ACAT website, and you should check there for the most up-to-date requirements before you file. Once your application is accepted, ACAT will usually schedule a conciliation conference first, giving both sides a chance to settle before a formal hearing. If conciliation does not resolve the dispute, the matter proceeds to a hearing where both parties present evidence and the tribunal makes a binding decision.
Evidence that helps your case
Strong evidence is the foundation of a successful dispute. Collect and organise:
- your signed building contract and any appendices or schedules
- all written variation requests, quotes and approvals — or correspondence showing a variation was never agreed
- progress claim invoices and any payment schedule or payment claim notices issued by the builder
- photographs of the work at the stage the progress claim was issued
- emails, texts or letters between you and the builder discussing the variation or payment
- an independent builder’s or quantity surveyor’s report on the value of work completed or the reasonableness of the charge
A clear, chronological written summary of events also helps the tribunal follow your case quickly.
How Claim Done helps
Before you file with ACAT, sending the builder a professionally drafted letter of dispute can prompt a resolution without the time and stress of a hearing. Claim Done prepares a clear, firm written dispute letter tailored to your ACT building contract situation — setting out what you contest, why the variation or progress claim is not payable as presented, and what you require the builder to do next. Having your position in writing also becomes a key piece of evidence if the matter does proceed to ACAT.
What happens when you put the builder on formal notice
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Dispute a Builder's Variation, Overcharge or Progress Claim drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Dispute a Builder's Variation, Overcharge or Progress Claim from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=builder-variation-dispute. Claim Done is not a law firm and does not give legal advice.
How much does a Dispute a Builder's Variation, Overcharge or Progress Claim cost, and how long does it take?
$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.
Do I need a lawyer to send a Dispute a Builder's Variation, Overcharge or Progress Claim in Australia?
No. There is no legal requirement to use a solicitor to write or send a Dispute a Builder's Variation, Overcharge or Progress Claim; many people send their own. Claim Done drafts it for you and you approve it before it is sent.