If you are a South Australian homeowner who believes a builder has charged for an unauthorised variation, inflated a progress claim, or billed for work not agreed in writing, the South Australian Civil and Administrative Tribunal (SACAT) is the forum designed to resolve that kind of dispute without the cost of going to court. SACAT has jurisdiction over residential building disputes in South Australia and can make binding orders against builders and contractors.
How SACAT Decides a Variation or Progress-Claim Dispute
When SACAT considers a dispute about a builder’s variation or progress claim, it looks at the building contract as a whole — including any written variations that were properly authorised — and compares what was agreed with what has been charged. Key things the tribunal examines include:
- Whether the variation was agreed in writing before the work was carried out, as generally required under South Australian building law for residential work
- Whether the amount claimed for the variation or progress stage is consistent with the original contract price and scope
- Whether the builder gave the homeowner proper notice before carrying out additional or changed work
- Whether the work the subject of the progress claim has actually been completed to the standard required by the contract
- Whether any alleged overcharge reflects a genuine change in scope or is a unilateral price increase
SACAT will consider evidence from both sides and may hear from experts where the dispute involves technical building questions. The tribunal applies South Australian residential building legislation and the terms of the contract itself.
Orders SACAT Can Make
SACAT has broad powers to resolve building payment disputes. Depending on the facts, the tribunal may order that:
- A disputed variation charge be reduced or set aside entirely
- A progress payment be adjusted to reflect only the work actually completed
- Money already paid by the homeowner be refunded
- A builder complete specified work before any further payment falls due
- The parties comply with particular terms of their contract
The tribunal aims to reach a fair outcome that reflects the contract the parties actually made, not the one the builder now claims was agreed.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who did the work?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
How to Apply to SACAT
Before applying, South Australian building legislation generally requires parties to attempt to resolve the dispute directly. If that fails, you can lodge an application with SACAT. The general process is:
- Gather your contract, variation documents, payment claims and any correspondence with the builder
- Download the correct application form from the SACAT website — the right form depends on whether your dispute falls under the building jurisdiction or a related consumer category
- Pay the application fee shown on the SACAT website (fees vary by claim type and are updated periodically, so check the current schedule at sacat.sa.gov.au)
- Serve a copy of your application on the builder as directed by SACAT
- Attend any conciliation or hearing scheduled by the tribunal — many disputes settle at the conciliation stage
Do not state a specific fee here — always check the current fee schedule on the SACAT website before lodging.
Evidence That Helps Your Case
Strong evidence is the foundation of a successful application. Useful documents include:
- Your signed building contract and any formal variation agreements
- Written quotes or cost estimates for the disputed work
- Emails, texts or letters in which the variation was (or was not) agreed
- Photographs showing the actual state of the work at the time the progress claim was issued
- An independent building inspection report if the quality or completion of work is in question
- Invoices or receipts that show what materials or labour actually cost
Organising this evidence clearly and chronologically makes it much easier for the tribunal — and any conciliator — to understand your position quickly.
How Claim Done Helps
A well-drafted formal letter to your builder — setting out exactly which variation or progress claim you dispute, why it is not supported by the contract, and what you are asking the builder to do — can resolve the matter before you ever need to file at SACAT. Claim Done prepares that letter for you at a flat fee, using the facts you provide. Having the right document on file also strengthens your SACAT application if the dispute does proceed, because it shows you gave the builder a clear opportunity to respond before escalating.
What happens when you put the builder on formal notice
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Dispute a Builder's Variation, Overcharge or Progress Claim drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Dispute a Builder's Variation, Overcharge or Progress Claim from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=builder-variation-dispute. Claim Done is not a law firm and does not give legal advice.
How much does a Dispute a Builder's Variation, Overcharge or Progress Claim cost, and how long does it take?
$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.
Do I need a lawyer to send a Dispute a Builder's Variation, Overcharge or Progress Claim in Australia?
No. There is no legal requirement to use a solicitor to write or send a Dispute a Builder's Variation, Overcharge or Progress Claim; many people send their own. Claim Done drafts it for you and you approve it before it is sent.