If a builder has charged you for a variation you never agreed to, inflated a progress claim, or demanded payment you believe is not owed under your contract, the Queensland Civil and Administrative Tribunal (QCAT) is the forum where most residential building payment disputes are resolved. QCAT is an accessible, lower-cost alternative to court, and it handles disputes between homeowners and builders over money claimed or withheld under a domestic building contract.
For the forms, fees and each step, see our guide to making an QCAT application.
How QCAT Decides a Variation or Progress Claim Dispute
QCAT examines the building contract itself as its starting point. In Queensland, residential building work is governed by the Queensland Building and Construction Commission framework, and all domestic building contracts above a certain value must meet minimum requirements — including rules about how variations must be documented and agreed. The tribunal will look at:
- Whether the variation was properly authorised in writing before the work was carried out
- Whether the original contract price was correctly applied to each progress-claim stage
- Whether the work claimed for was actually completed to the required standard at the time of the claim
- Whether any disputed amount was genuinely a variation or was already included in the contract scope
- The conduct of both parties — including any representations made on site or by email
QCAT may appoint a building expert to inspect work or assess costs where the technical facts are genuinely in dispute. It applies the law in a practical, evidence-based way and does not require you to have a lawyer, although you may bring one with leave of the tribunal.
Orders QCAT Can Make
Once QCAT hears the matter, the tribunal may order a range of outcomes, including:
- That a disputed variation amount is not payable by the homeowner
- That the builder repay money already paid that was not properly owing
- That a reduced amount is payable where only part of the variation or claim is upheld
- That work must be completed or rectified before a progress payment becomes due
- Declaratory orders clarifying the rights of each party under the contract
QCAT cannot award unlimited damages — its jurisdiction has a monetary ceiling. If your dispute involves a very large sum, check the current jurisdictional limits on the QCAT website or seek legal advice about whether the Supreme or District Court is more appropriate.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who did the work?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
How to Apply to QCAT
Applications are made using QCAT’s official forms, which are available on the QCAT website along with the current filing fees. You will need to identify the correct application type for a building dispute. Once lodged, QCAT will generally schedule a preliminary conference where a registrar tries to help the parties reach an agreement. If that fails, the matter proceeds to a hearing before a member. You should apply promptly — building disputes have limitation periods, and delay can complicate your case or affect your rights. Always check the QCAT website for up-to-date forms, fees and procedural requirements before lodging.
Evidence That Helps Your Case
Strong, organised evidence is the most important thing you can bring to QCAT. Gather and keep:
- Your signed building contract and any formal variation documents
- All written communications — emails, text messages, letters — about the disputed work
- Photographs of the work at each stage, dated where possible
- Progress-claim invoices and your payment records
- Any independent quotes or assessments of the work in question
- A clear written timeline of events, in chronological order
If you disputed the variation or claim at the time, contemporaneous records of that objection are especially valuable.
How Claim Done Helps
A clearly written, legally structured letter of dispute to your builder — prepared before or alongside your QCAT application — sets out your position on the record and can prompt resolution without a hearing. Claim Done’s builder dispute letter is drafted to address the key issues QCAT looks at: contractual authority for the variation, compliance with documentation requirements, and the amounts genuinely in dispute. Having this document ready strengthens your application and shows the tribunal that you raised the issue formally and in good faith.
What happens when you put the builder on formal notice
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Dispute a Builder's Variation, Overcharge or Progress Claim drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Dispute a Builder's Variation, Overcharge or Progress Claim from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=builder-variation-dispute. Claim Done is not a law firm and does not give legal advice.
How much does a Dispute a Builder's Variation, Overcharge or Progress Claim cost, and how long does it take?
$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.
Do I need a lawyer to send a Dispute a Builder's Variation, Overcharge or Progress Claim in Australia?
No. There is no legal requirement to use a solicitor to write or send a Dispute a Builder's Variation, Overcharge or Progress Claim; many people send their own. Claim Done drafts it for you and you approve it before it is sent.