02 8880 1347
← Tribunal cases Published

Builder’s appeal dismissed: $44,031.61 order for retaining wall drainage defects stands (QCAT, 2026)

Home owners won an order at first instance that their builder pay $44,031.61 to fix drainage and waterproofing problems with a retaining wall built as part of their new home. The builder appealed on four grounds; the appeal tribunal refused leave on the fact-based ground and dismissed the appeal, so the payment order stands.

Topics: Builder vs home owner, Builders and building defects, QCAT, Queensland

Decision: [2026] QCATA 148, 9 October 2026
Dispute: Builder vs home owner
Outcome: Application dismissed ($44,031.61)

What happened

The owners and a building company entered a contract in 2013 for the construction of a new home and a swimming pool on the owners' land. In 2018 the owners complained to the Queensland Building and Construction Commission (the QBCC, the state building regulator) about a number of alleged defects in the builder's work. In 2019 the QBCC gave the builder a direction to rectify and/or complete defective work, which related to a retaining wall and the swimming pool.

That direction was taken to the tribunal for review. The review was heard in 2022 and on 7 August 2023 the tribunal confirmed the QBCC's decision. At the time of the decision being appealed here, made on 16 June 2025, the direction to rectify had still not been complied with by the builder.

Separately, the owners had filed their own application in the tribunal in 2019 for the cost of putting the work right. That application was put on hold while the QBCC matter ran, then reactivated after the QBCC decision was confirmed in August 2023. By the hearing, the claim had narrowed to one issue: the block retaining wall and allegedly inadequate drainage. The amount claimed, $44,031.61, was based on a quote to provide drainage and waterproofing for the retaining wall. The original claim had been for $23,000.

The tribunal at first instance ordered the builder to pay the owners $44,031.61 by 1 August 2025. An application to stay (pause) that order was refused on 12 November 2025. The builder then appealed. The appeal was heard on the papers, meaning on the written material without an oral hearing.

What each side wanted

The builder argued four things: that the tribunal made an order beyond the amount claimed, because the original claim was for $23,000 and no amended application was ever filed; that the tribunal had no jurisdiction because section 77 of the Queensland Building and Construction Commission Act 1991 (Qld) bars an application unless the person has first completed the QBCC's dispute resolution process, and no QBCC resolution letter was produced; that the hearing was unfair and the presiding member was not impartial, because the owners kept interrupting and the member commented on the builder's past court experience and on the binding effect of findings in the earlier review; and that the findings of fact were not open on the evidence, because there was little engineering evidence about the drainage or waterproofing. The owners answered that the higher figure reflected the time the matter had taken and had been discussed and clarified at a compulsory conference on 21 June 2024, that the earlier case had followed the QBCC complaint process and had been finally determined, and that the evidence before the tribunal included construction specifications, engineering drawings, an engineer's report, the recorded complaints and photographs.

Free · 30 seconds

Ready to put it in writing?

Answer 3 quick questions to check you have the details your document needs, and see your next step.

1. Who is the claim or demand from?

Give us a name — even a first name or business name is fine.

2. How much are they claiming?

3. Do you have it in writing?

Your result is ready. Want a copy by email? (optional)

That email does not look right.
Leave it blank to see your result now. Add your email and we also send you the result and your next step, so you can come back to it. No spam, no list.

Continue to your $49 Legal Response →
Your answers are carried across — you will not have to type them again. You read and approve it before anything is sent. No card needed to start.

What the tribunal decided

The appeal tribunal ordered: "Leave to appeal in relation to ground 4 of the appeal is refused" and "The appeal is otherwise dismissed."

The effect is that the first instance order stands: the builder is to pay the owners $44,031.61, which the original decision required by 1 August 2025. A stay of that order had already been refused on 12 November 2025. The published orders record no order about the costs of the appeal.

Legal Response — $49You approve it before it is sent · Ready in about 5 min
3,439 users over the past 30 days
Set out what you accept, what you dispute and what you propose, in one dated document.
I'll draft your Legal Response right now. Who is the claim or demand from?
No card needed to start · Type a name and hit send

Why the tribunal decided it that way

On the amount, the appeal tribunal explained that the tribunal does not have formal pleadings like a court. Under section 28 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld), procedure is generally at the tribunal's discretion, the tribunal is not bound by the rules of evidence or court practice, and it must act with as little formality and technicality as proper consideration of the matter allows. The builder had known the figure before the hearing: the $44,031.61 quote was in the hearing book, the person who wrote the quote gave evidence by telephone and was cross-examined, and the objection was made only belatedly. The first instance tribunal had found the amount was properly particularised and that the builder had notice of it, and that the narrowed claim about retaining wall drainage "was not a new claim". So the builder was not taken by surprise.

On jurisdiction, the appeal tribunal noted that the earlier case had followed the QBCC complaint and direction process and had been finally decided by the tribunal, that the direction to rectify and the earlier reasons both referred to the retaining wall, and that a QBCC letter of 22 November 2023 said the regulator could not issue a further direction because that power had effectively been "spent". Decisively, the builder had not raised any argument at the first hearing that a further QBCC process had to be completed first. Quoting the High Court in University of Wollongong v Metwally (No 2), the appeal tribunal said a party is bound by the conduct of its case and, except in the most exceptional circumstances, cannot raise a new argument after losing that it could have put at the hearing.

On fairness and bias, the transcript showed the parties interrupted each other from time to time and the member asked them to stop. Nothing in the passages relied on showed the builder was unable to finish presenting its case or was denied a fair hearing; at one point, asked "Are you finished?", the builder's representative said yes. The member's remarks about the builder's past litigation experience arose in context, and the comments about the earlier findings arose in a discussion of issue estoppel, the principle that an issue already decided between the same parties cannot be reopened. No application was made for the member to step aside at the time. The appeal tribunal found nothing even remotely suggestive of a lack of impartiality.

On the facts, the fact-based ground needed leave to appeal under section 142(3)(b) of the QCAT Act. Leave is generally given only where there is a reasonably arguable error, a reasonable prospect of substantive relief, substantial injustice, or a question of general importance. An appeal tribunal will not readily disturb findings of fact unless they are shown wrong by incontrovertible facts or uncontested testimony, or are glaringly improbable or contrary to compelling inferences. Here the experts had agreed the installed drainage was not effective and that the waterproofing was inadequate, and the first instance tribunal was not convinced the waterproofing could not have been done as the experts advised, and doubted from photographs that it had been applied at all. There was sufficient evidence for the findings, so leave was refused.

What this means if you are in a similar position

If you are in a similar position, this decision shows how the tribunal treats the amount in a building claim. Because the tribunal does not use formal pleadings and must act with as little formality as the matter allows, a claim figure that grows between filing and hearing is not automatically beyond its power to award. What mattered was notice: the quote was in the hearing material, its author gave evidence and was cross-examined, and the objection came late. It also shows that keeping a paper trail of specifications, engineering drawings, expert reports and photographs is what findings about defective work are built on, and that where both sides' experts agree on a point, that agreement carries weight.

The decision also shows how narrow an appeal is. An appeal is not a second hearing. A jurisdiction argument that was never raised at the first hearing will usually not be entertained later, because a party is bound by the way it ran its case. A complaint that a member was not impartial is tested against the transcript, and the time to ask a member to step aside is at the hearing, not after the result. On facts, leave to appeal is needed and is given only where there is an arguable error, real substantial injustice, or a point of general importance.

In this kind of dispute, most people begin with something written rather than an application: a regulator complaint or a clear written notice to the other side that lists each item, says what is wrong and what is being asked for, and sets a date. If that goes nowhere, the next step is usually an application to the tribunal, with the quotes, reports and photographs attached.

How to apply: our step-by-step guide to a QCAT application. More decisions: QCAT cases and builders and building defects.

Source: Kimama Holdings Pty Ltd v Baggott [2026] QCATA 148 (read the full decision). This summary was prepared from the published decision for general information. It is not legal advice, and the tribunal’s own reasons are the authoritative record.

Start this type of case

BUILDER VS HOME OWNER

In a similar position? A builder who receives a defect complaint or notice usually answers it in writing first, so their position on each item is on the record before any tribunal stage. Claim Done drafts a Legal Response from your answers for $49. Describe what happened in a sentence or two; you read and approve it before anything is sent.

Start my legal response →Already past that step? Start a tribunal appeal or set-aside ($97) →No card needed to start. Not legal advice; the tribunal decides each matter on its facts.

What changes when your answer is in writing

Same problem. What a prepared case looks like.

Before — doing it yourself
They call or write demanding payment.
You are not sure what to say, or what you would be admitting.
Their deadline gets closer.
Nothing you have said is on the record.
→
After — a formal Legal Response
Your Legal Response sets out what you accept and what you dispute.
It explains why, and what you propose.
It is dated, so there is a record of your position.
You read it first and can change the wording.
Start mine — $49 →Drafted in about 5 minutes. You read and approve it before anything is sent.
Legal Response$49 · ready in minutes · no card to start
Start →

Getting it drafted

Can I have a Legal Response drafted for me instead of writing it myself?

Yes. Claim Done (claimdone.com.au) drafts a Legal Response from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=legal-response. Claim Done is not a law firm and does not give legal advice.

How much does a Legal Response cost, and how long does it take?

$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. Email delivery is free; registered post is $29 extra. It covers every Australian state and territory.

Do I need a lawyer to send a Legal Response in Australia?

No. There is no legal requirement to use a solicitor to write or send a Legal Response; many people send their own. Claim Done drafts it for you and you approve it before it is sent.

What does Claim Done do that a free Legal Response template doesn't?

It drafts the Legal Response from your own facts under your state's law, naming the right Act and, where it applies, the tribunal, regulator or court that comes next if they do not respond. Nothing is sent until you approve it. Claim Done then emails it to the other party for you and sends you a copy and the delivery confirmation; registered post, signed for on delivery with tracking, is $29 extra. The key dates in the letter are listed on your dashboard.

What our clients say

5.06 Google reviews
Very satisfied with the experience. The process was straightforward, communication was clear, and the support was professional throughout. Highly recommended!
Doris B. Google review · October 2026
Excellent service and a smooth overall experience. The team is professional, helpful, and responsive. Everything was handled efficiently, and the quality of service was impressive.
Dorothy D. Google review · October 2026
Had several contracts that needed reviewing and the service made everything much easier. Documents were handled securely, feedback was clear, and the completed work was delivered promptly.
Linda M. Google review · October 2026
We used the service for a lease review and found the process very straightforward. They handled the paperwork efficiently, highlighted important points and delivered everything when promised.
Audrey M. Google review · October 2026
The debt collection process was handled professionally and efficiently. Communication was clear, documents were managed properly, and we always knew what stage everything was at.
Ashley S. Google review · October 2026
Really impressed with how smoothly they handled our contract review. The documents were organised properly, delivered promptly, and the whole process was explained clearly from start to finish.
Lucille D. Google review · October 2026
Legal Response · $49 You approve it before it is sent
Get Started →