Builder ordered to fix mortar, mould and render, but owner’s delay damages claim dismissed (SAT, 2026)

A home owner who refused to accept that his new house was finished took a list of defects and a claim for delay damages against WA Country Builders Pty Ltd. The tribunal ordered the builder to fix the mortar, a beam tie-down, mould in the garage and poor render on an outdoor kitchen wall, but dismissed the moisture, brick staining and delay damages claims.

Not sure what you need? Just tell us what happened. Describe it in plain English and our chat builds the right document for you — no forms, no legal jargon.

Drafted from your answers in minutes · you review it before anything is sent · Private & encrypted

Topics: Builders and building defects, Home owner vs builder, SAT, Western Australia

Decision: [2026] WASAT 103, 14 July 2026
Dispute: Home owner vs builder
Outcome: Partly successful
You have two ways to deal with this:One of them is done for you.
Do it yourself
Free — if you get it right
Hours of research
Easy to cite the wrong law
Easy to leave out a firm deadline
Done for you
Claim Done
$79 flat. That is it.
Ready in about 5 minutes
Cites the law for your state
You approve it before it is sent
Start now — $79 →
A lawyer's letter
Typically $500 to $1,500
Days to arrange
Legal advice on your matter

What happened

In December 2020 the owner signed a fixed-price contract of $276,354 with WA Country Builders Pty Ltd to build a house in the City of Busselton area. The contract said the work was to be finished within 350 working days of starting. The tribunal accepted the owner's evidence that work started on 14 June 2021. Both sides also appeared to accept that the builder had validly extended the time for completion by 119 working days.

A document called a Record of Practical Completion was signed by both parties on 20 April 2023. 'Practical completion' is the point at which a building is treated as finished, apart from minor items that do not stop it being used. On 8 May 2023 the owner emailed to try to withdraw his signature. The builder said it lodged a notice of completion with the City of Busselton around 9 May 2023, but the tribunal was not satisfied the evidence proved this. The owner then disputed the final invoice, saying the build was not finished. The builder agreed to hold the invoice until the remaining work was done.

Through mid to late 2023 the parties argued by email about outstanding repairs, how the completion date should be calculated, whether delay damages were owed and how much the owner still had to pay. On 5 October 2023 the builder offered to accept payment in two instalments and said the owner could collect the keys once the first was paid. The owner made a final payment on 6 October 2023, without admitting he owed it, and collected the keys that day. Because of concerns about dampness and mould, he did not move in until 31 December 2025.

The owner made complaints to the Building Commissioner, who referred ten complaint items to the tribunal. During the hearing, after hearing the expert evidence, the owner withdrew three items. That left seven items for decision.

What each side wanted

The owner said the builder's work was faulty in several ways: missing, stained and eroding mortar on the outside brickwork; a beam tie-down in the garage that was not properly welded; excessive moisture throughout the house; mould on the garage brickwork and outside bricks; unsightly staining and bleach marks on the brickwork; and poorly applied render on the back wall of an outdoor kitchen recess. He also claimed liquidated damages, which are a fixed amount set by a contract that the builder pays for each day it is late, plus his costs of owning the property while he waited. He argued the house never reached practical completion, but limited his claim to the period up to 31 December 2025, when he moved in. The builder admitted the tie-down fault and accepted some mortar faults. It agreed the garage was damp but said a garage is not meant to be as dry as a house and that normal use and airflow would reduce the moisture. It did not deny that there was mould. It argued practical completion was reached on 30 March 2023, 20 April 2023 or around 9 May 2023, and so no delay damages were owed.

Free · 30 seconds

Ready to put it in writing?

Answer 3 quick questions to check you have the details your document needs, and see your next step.

1. Who did the work?

Give us a name — even a first name or business name is fine.

2. How much is at stake?

3. Do you have it in writing?

Your result is ready. Want a copy by email? (optional)

That email does not look right.
Leave it blank to see your result now. Add your email and we also send you the result and your next step, so you can come back to it. No spam, no list.

Continue to your $79 Defects Notice to Your Builder →
Your answers are carried across — you will not have to type them again. You read and approve it before anything is sent. No card needed to start.

What the tribunal decided

The tribunal ordered WA Country Builders Pty Ltd to complete four sets of repairs by 14 October 2026:

(a) Mortar: fix the face brickwork mortar joints so they are fully filled without voids, in line with AS3700-2018, Part 12.4.2. Patching is to match nearby brickwork as closely as practicable, joints are to have a consistent finish, and no mortar stains are to be visible from 1.5 metres. Holes the owner drilled to take samples were excluded. (b) Tie-down: fix the unsecured steel beam in the garage in line with the engineering plans. (c) Mould: remove the mould from the internal brick surfaces of the garage. (d) Outdoor kitchen: fix the render on the wall of the barbeque recess so that it achieves an acceptable appearance. The work must be done in a proper and proficient manner, including protecting and making good all affected surfaces.

All other complaints, including the moisture, brick staining and damages claims, were dismissed. No money was ordered to be paid. Each party may apply for its legal costs by filing a detailed schedule and written submissions by 4 August 2026. The other party may respond by 25 August 2026. Any costs application will then be decided on the documents alone.

Defects Notice to Your Builder — $79You approve it before it is sent · Ready in about 5 min
6,284 people visited ClaimDone in the past 30 days
A formal letter is the first thing the tribunal and the builder's licensing body will ask whether you sent.
I'll draft your Defects Notice to Your Builder right now. Who is this about?
No card needed to start · Type a name and hit send

Why the tribunal decided it that way

The tribunal explained that the Building Services (Complaint Resolution and Administration) Act 2011 (WA) allows two kinds of complaint. A 'building service complaint' is about faulty work. Under s 38(1), the tribunal must order repairs if the work was not done in a proper and proficient manner, or is faulty or unsatisfactory. A 'home building work contract complaint' is about breaches of the contract. Under s 43(1) and s 41, the tribunal may order payment of amounts due under the contract or compensation if it considers this justified. Six of the remaining items were building service complaints and the damages claim was a contract complaint.

On the mortar, the Building Commissioner had proposed repairs, which the builder appeared to accept, and both engineers agreed some mortar was missing or inadequate. There was no evidence of erosion, and chemical testing showed the mortar mix was appropriate. The builder admitted the tie-down fault. On the moisture claim, the tribunal was not satisfied there was elevated moisture inside the house. It found problems with some of the readings, and there were no signs of rising damp or stormwater damage. The garage was damp, but a garage is a non-habitable structure and single-skin brick walls are expected to let some outside moisture through. The house had also stood empty with no normal airflow. On the brick staining, the evidence did not show what caused the discolouration, so the tribunal could not find the builder at fault. On the render, the parties had agreed it was to improve the look of the wall, and it had not been applied in a way that achieved this.

On the mould, the tribunal found the builder kept possession and control of the house until it handed over the keys on 6 October 2023. That made it responsible for the condition of the house, including cleaning the gutters, until then. The tribunal said it is not satisfactory to hand over a house with mould growing on the internal garage walls. The builder had not argued that the owner failed to take reasonable steps to limit the problem, so that could not be considered. There was not enough evidence of mould on the outside bricks.

On delay damages, the tribunal calculated the contract deadline, including the 119-day extension, as 28 April 2023. Under clause 12.6 of the contract, practical completion occurs at the earliest of three events: the work is finished apart from defects that do not stop it being used; the owner takes possession without consent; or the builder hands over the keys. The tribunal rejected 30 March 2023 because no one signed the document on that day. It found practical completion was reached on 20 April 2023, when both parties signed. Nothing in the signed record or the final inspection report suggested the house was unfit to live in, and neither mentioned mould. The builder's later repairs were work it had agreed to do to settle the owner's concerns, not a delay to completion. Because the house was finished in time, no liquidated damages were payable. Choosing to wait until repairs were done before moving in did not make the builder liable for the owner's costs.

What this means if you are in a similar position

This decision shows that the tribunal looks at each defect separately and needs evidence linking the problem to the builder's work. If you are in a similar position, you may find that defects the builder admits, or that experts agree on, are more likely to lead to repair orders. Claims about the cause of a problem, such as moisture or staining, can fail if the evidence does not show why it happened. Here, the tribunal gave less weight to reports whose authors were not called to give evidence, and to tests where it was unclear how or where samples were taken.

The decision also shows how a contract's own definition of practical completion can decide a delay claim. In this case, signing a Record of Practical Completion counted heavily, even though the owner later tried to withdraw his signature and the builder kept doing repairs afterwards. The decision also shows that who controls the site matters. The builder was held responsible for the house's condition until it handed over the keys.

In general, people in a building dispute in Western Australia usually start by setting out the defects in a written notice to the builder. If that does not resolve things, the next step is usually a complaint to the Building Commissioner, who can refer it to the tribunal.

How to apply: our step-by-step guide to a SAT application. More decisions: SAT cases and builders and building defects.

Source: Poole and Wa Country Builders Pty Ltd (Acn 105 402 140) [2026] WASAT 103 (read the full decision). This summary was prepared from the published decision for general information. It is not legal advice, and the tribunal’s own reasons are the authoritative record.

Start this type of case

HOME OWNER VS BUILDER

In a similar position? Owners of a finished home with defects the builder won't fix usually begin with a formal defects notice listing each item before any regulator complaint. Claim Done drafts a Defects Notice to Your Builder from your answers for $79. Describe what happened in a sentence or two; you read and approve it before anything is sent.

Start my defects notice to your builder →Already past that step? Start a building dispute pack: notice, regulator complaint and evidence schedule ($97) →No card needed to start. Not legal advice; the tribunal decides each matter on its facts.

What happens when you put the builder on formal notice

Same problem. What a prepared case looks like.

Before — doing it yourself
You text them. "I'll be there next week."
Next week comes. Nothing.
They stop answering. You are out of pocket.
You wonder if it is worth the fight.
→
After — a formal Defects Notice to Your Builder
A formal Defects Notice to Your Builder lands in their inbox.
It sets out what was agreed and what is still not done.
They have a fixed deadline to fix it or refund.
If they do not, your notice is the first piece of evidence for the tribunal.
Send mine — $79 →Drafted in about 5 minutes. You read and approve it before anything is sent.
Defects Notice to Your Builder$79 · ready in minutes · no card to start
Start →

Getting it drafted

Can I have a Defects Notice to Your Builder drafted for me instead of writing it myself?

Yes. Claim Done (claimdone.com.au) drafts a Defects Notice to Your Builder from the answers you give about your situation for a flat $79 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=home-building-defects-claim. Claim Done is not a law firm and does not give legal advice.

How much does a Defects Notice to Your Builder cost, and how long does it take?

$79 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. Email delivery is free; registered post is $29 extra. It covers every Australian state and territory.

Do I need a lawyer to send a Defects Notice to Your Builder in Australia?

No. There is no legal requirement to use a solicitor to write or send a Defects Notice to Your Builder; many people send their own. Claim Done drafts it for you and you approve it before it is sent.

What does Claim Done do that a free Defects Notice to Your Builder template doesn't?

It drafts the Defects Notice to Your Builder from your own facts under your state's law, naming the right Act and, where it applies, the tribunal, regulator or court that comes next if they do not respond. Nothing is sent until you approve it. Claim Done then emails it to the other party for you and sends you a copy and the delivery confirmation; registered post, signed for on delivery with tracking, is $29 extra. The key dates in the letter are listed on your dashboard.

What our clients say

5.09 Google reviews
The team provided helpful support and maintained clear communication throughout the process. Everything was explained in a straightforward way, making the experience easy to follow.
Fabrice L. Google review · November 2026
Really good service with a professional approach and clear communication. The experience was pleasant, and the attention to detail stood out.
Catherina D. Google review · October 2026
The service was professional and the overall experience was smooth. Communication was clear, and everything was handled efficiently.
Ricardo R. Google review · October 2026
Very satisfied with the experience. The process was straightforward, communication was clear, and the support was professional throughout. Highly recommended!
Doris B. Google review · October 2026
Excellent service and a smooth overall experience. The team is professional, helpful, and responsive. Everything was handled efficiently, and the quality of service was impressive.
Dorothy D. Google review · October 2026
Had several contracts that needed reviewing and the service made everything much easier. Documents were handled securely, feedback was clear, and the completed work was delivered promptly.
Linda M. Google review · October 2026
We used the service for a lease review and found the process very straightforward. They handled the paperwork efficiently, highlighted important points and delivered everything when promised.
Audrey M. Google review · October 2026
The debt collection process was handled professionally and efficiently. Communication was clear, documents were managed properly, and we always knew what stage everything was at.
Ashley S. Google review · October 2026
Really impressed with how smoothly they handled our contract review. The documents were organised properly, delivered promptly, and the whole process was explained clearly from start to finish.
Lucille D. Google review · October 2026
Defects Notice to Your Builder · $79 You approve it before it is sent
Start My Notice →