A Scott Schedule is a table that lists each building defect on its own numbered row, with what the work should have been, what is wrong, what it costs to fix, and space for the builder’s reply and the tribunal. NCAT, QCAT and the WA State Administrative Tribunal (SAT) publish their own forms. To prepare one, take your defects one at a time, keep each row specific, and put your evidence and cost beside each item.
For the forms, fees and each step, see our guide to making an NCAT application.
Claim Done drafts the owner’s own building defects schedule from your answers for a flat A$79, with a short note on how to use it. This guide covers each tribunal’s form, the steps before the tribunal, and how to fill it in. It is general information, not legal advice.
What a Scott Schedule is
NCAT’s Home Building Applications guideline describes a Scott Schedule as a form that lets parties itemise defective and incomplete works in a home building dispute. It says schedules are generally used in complex matters or where there are a number of defects, and that the Tribunal may make directions about filing evidence, including expert reports, a Scott Schedule and a chronological bundle of documents.
The State Administrative Tribunal in Western Australia puts it simply: the applicant lists each complaint, with the applicant’s and the respondent’s position next to each item. SAT says the schedule can be in any format that complies with its orders.
Your schedule is not an expert report
The schedule is a working list from the parties. NCAT’s form has separate columns for the applicant, the respondent and the tribunal member. SAT’s form says the applicant must complete its own part, and the applicant lists the evidence it relies on for each item, and SAT gives “expert reports, photographs, quotations/invoices” as examples. In other words, an expert report is separate evidence that your schedule points to.
Tribunals may require expert evidence. NCAT’s guideline says applicants should only apply when they are ready, “having obtained all the necessary experts reports”. NCAT’s Procedural Direction 3 sets rules for experts in home building claims where more than $30,000 is claimed or in dispute (as at November 2026), and says an expert’s paramount duty is to the Tribunal, not to the party who hired them. At an NCAT conclave, the experts may draft and sign a joint Scott Schedule.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who is this about?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
The columns each tribunal’s form uses
Here is the column order each official form shows, read in November 2026, with some long headings shortened.
| State | Official form | Columns, in the form’s order |
|---|---|---|
| NSW (NCAT) | Scott Schedule – Defective workmanship or material claimed | Item No.; Contract; Applicant: Comments; Applicant: Estimate of Loss; Respondent: Comments; Respondent: Estimate of Loss; Tribunal Member’s Comments |
| Queensland (QCAT) | Alleged defective work/incomplete work schedule | Item number; Description of defective work/incomplete work; Builder notified of defect (Yes/No and Date); Date first noticed |
| WA (SAT) | Complaint Schedule: Building Dispute matters | 1 Item No.; 2 Location or contract issue; 3 Description of complaint item; 4 Specific work required; 5 Work order or money order; 6 Amount of money claimed; 7 Applicant’s evidence; 8 to 11 for the respondent |
| Victoria (VCAT) | No schedule form in the practice note read | VCAT’s practice note asks for itemised particulars instead (see below) |
NCAT’s forms page also lists a separate Scott Schedule for extras claimed. For South Australia, Tasmania, the ACT and the Northern Territory, no official schedule guidance was read for this guide: follow any direction the tribunal or court gives, and ask its registry.
Steps that come before the tribunal
Queensland: QBCC first
QCAT says parties must take part in a dispute resolution process with the Queensland Building and Construction Commission (QBCC) before applying, and must give QCAT the QBCC letter. Without it, QCAT may refuse or dismiss the application. The QBCC calls lodging a complaint with it a mandatory first step. If you want defective work fixed or incomplete work finished, QCAT says you must complete its schedule and attach it to your application (Form 26 for domestic building disputes). If you already completed a QBCC complaint form, QCAT’s form says you can provide a copy of that instead.
Victoria: DBDRV first
VCAT says it cannot help with a home owner’s domestic building dispute that has not been to Domestic Building Dispute Resolution Victoria (DBDRV), unless you are applying for an injunction. VCAT says the Building and Plumbing Commission now brings together DBDRV’s powers and responsibilities; check its steps with it directly. VCAT’s Practice Note PNBP1 (effective 1 February 2026) says points of claim should give fully itemised particulars and clearly identify any incomplete and defective works, and that any available expert report should go with the application.
Western Australia: the Building Commissioner
SAT says the Building Commissioner can refer or transfer matters to it. For a referred complaint, SAT’s form says columns 1 to 3 must be identical to the first three columns of the list of complaint items lodged with the Building Commissioner, and the applicant may not change or expand them. SAT’s Info Sheet 17 says that in a building service complaint (alleged faulty or unsatisfactory building work) the applicant is usually ordered to prepare a complaint schedule using SAT’s templates.
New South Wales: be ready before you apply
NCAT’s guideline says applications must be lodged within the time limits in sections 48K and 18E of the Home Building Act 1989. If a party does not provide documents as the Tribunal directs, it may not be able to rely on them at the hearing without permission.
How to prepare your schedule, step by step
- Number every defect, one per row. Use the same numbers on your photos.
- Say exactly where it is. QCAT asks for each item to be “individually numbered and specific in detail”: which room, which wall, how high.
- Say what the work should have been. NCAT’s Contract column asks what should have been done under the contract, specification or a variation, or to finish the work in a good and workmanlike manner if quality was not specified.
- Describe the defect plainly: what you can see, not your theory of the cause.
- Give your cost and its source. NCAT’s form asks for the cost of rectification, or the loss of value because of the defect. Note whether each figure is a quote or from a report.
- List your evidence for each item: photo numbers, report page numbers, emails.
- Leave the builder’s and the tribunal’s columns empty. Those are for them.
What a finished schedule contains
This is the structure, not a filled-in example.
- Heading block: file number (if you have one), applicant, respondent, property address.
- One line saying what it is: the owner’s own schedule of alleged defects, not an expert report.
- The table: one row per defect, in your tribunal’s column order where it has a form.
- A total of the cost figures you have.
- Prepared by and date. QCAT’s own form also carries a signed declaration.
Mistakes to avoid
- Vague rows. “Bad tiling” is hard to answer. “Ensuite floor tiles cracked beside the shower” is not.
- Overstating. QCAT’s form warns that knowingly giving the registry documents containing false or misleading information is an offence under section 216 of the Queensland Civil and Administrative Tribunal Act 2009. Include only defects you can show.
- Changing WA’s first three columns for a referred complaint.
- Missing a direction’s deadline. NCAT’s guideline says that if you have a good reason you cannot meet the timetable, write to the Registrar for an extension before the documents are due.
- Treating the schedule as your expert evidence. If an expert is needed, the expert’s report is separate.
What Claim Done’s schedule gives you
It is built from your answers, one numbered row per defect, and leaves the builder’s and tribunal member’s columns empty. In NSW it keeps NCAT’s columns in NCAT’s order, adding a location and an evidence column. In Queensland it adds a table in QCAT’s column order to copy onto QCAT’s form, which is the one you lodge. A one-page note explains how to use it in your State. Nothing is sent to anyone.
Ready to turn your list of defects into a clear numbered schedule? Start your defects schedule for A$79. Claim Done is not a law firm and this guide is not legal advice. For advice on your own case, contact Legal Aid or a community legal centre in your State.
What happens when you put it in writing — properly
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Building Defects Schedule (Scott Schedule) for Your Home Building Dispute drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Building Defects Schedule (Scott Schedule) for Your Home Building Dispute from the answers you give about your situation for a flat $79 AUD. You read and confirm the draft, then the final PDF is emailed to you. Start at claimdone.com.au/begin/?service=building-defects-schedule. Claim Done is not a law firm and does not give legal advice.
How much does a Building Defects Schedule (Scott Schedule) for Your Home Building Dispute cost, and how long does it take?
$79 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.
Do I need a lawyer to send a Building Defects Schedule (Scott Schedule) for Your Home Building Dispute in Australia?
No. There is no legal requirement to use a solicitor to write or send a Building Defects Schedule (Scott Schedule) for Your Home Building Dispute; many people send their own. Claim Done drafts it for you and you approve it before it is sent.