02 8880 1347
← Legal Guides Published · Updated

Progress Claim Ignored? How SOPA Adjudication Gets Subcontractors Paid Without Going to Court

A court case takes 18 months. Security of Payment adjudication takes about six weeks from the day you serve a payment claim to an enforceable decision. The full timeline, the deadlines you cannot miss, and how it plays out in every state.

Progress claim four went in at the end of the month, same as the first three. Claims one to three were paid, slowly. Claim four is now 45 days old and nobody at the builder’s office will say why. No dispute letter, no defects list, no “we’re withholding for X”. Just nothing. You’ve heard about adjudication but assumed it was for big contractors with lawyers on retainer.

It isn’t. Adjudication under the Security of Payment Acts was designed for exactly this: a subcontractor with a clean claim and a head contractor using silence as a financing strategy. No courtroom, no barrister, no discovery. You send documents, they send documents, an adjudicator decides. In most states the whole thing runs from payment claim to enforceable determination in about six to eight weeks.

You have two ways to deal with this:One of them is done for you.
Do it yourself
Free — if you get it right
Hours of research
Easy to cite the wrong law
Easy to leave out a firm deadline
Done for you
Claim Done
$49 flat. That is it.
Ready in about 5 minutes
Cites the law for your state
You approve it before it is sent
Start now — $49 →
A lawyer's letter
Typically $500 to $1,500
Days to arrange
Legal advice on your matter

Your rights

Every Security of Payment Act creates a two-track system. Track one is the statutory debt: if the respondent doesn’t serve a payment schedule in time, the full claimed amount becomes payable and you can go to court for summary judgment with the builder unable to argue the contract. Track two is adjudication: an independent adjudicator, nominated by an Authorised Nominating Authority (the QBCC registry in Queensland, a prescribed appointer in the Northern Territory), decides how much is payable. You can adjudicate whether the builder scheduled less, scheduled the right amount and didn’t pay, or never scheduled at all.

The decision binds on an interim basis: the builder must pay within a few business days, and if they don’t you file the adjudication certificate in court and it becomes a judgment. They can fight the underlying contract later, but they pay you first. Pay now, argue later. You also have the right to suspend work on short written notice without being liable for the delay.

The timeline, step by step

  1. Day 0: serve the payment claim. On the party liable under your contract, stating the work, period, amount and (outside Queensland) that it’s made under the Act.
  2. Day 10–15 (business days): payment schedule deadline. The builder schedules the full amount, schedules less with every reason written down, or does nothing.
  3. Due date. Fixed by the contract or the Act’s default (10 to 25 business days after the claim depending on state and contract tier).
  4. Adjudication window opens. Short schedule: 10 business days from receiving it in New South Wales, Victoria, South Australia, Tasmania and the Australian Capital Territory; 20 in Western Australia; 30 in Queensland. No schedule: New South Wales, South Australia and the Australian Capital Territory need a notice of intention within 20 business days after the due date, a 5-day second chance, then 10 business days to apply; Victoria and Tasmania have similar notices; Western Australia and Queensland allow 20 or 30 business days after the due date.
  5. Application lodged with the ANA or registry. Your claim, the contract, the schedule (if any) and a submission. An adjudicator is nominated within days.
  6. Response: 5 to 15 business days. Confined to the reasons already in the payment schedule.
  7. Determination: about 10 business days after the response.
  8. Payment or judgment: 5 business days. Unpaid determinations become judgments on filing the certificate.
Free · 30 seconds

Ready to put it in writing?

Answer 3 quick questions to check you have the details your document needs, and see your next step.

1. Who did the work?

Give us a name — even a first name or business name is fine.

2. How much is at stake?

3. Do you have it in writing?

Your result is ready. Want a copy by email? (optional)

That email does not look right.
Leave it blank to see your result now. Add your email and we also send you the result and your next step, so you can come back to it. No spam, no list.

Continue to your $49 SOPA Payment Claim →
Your answers are carried across — you will not have to type them again. You read and approve it before anything is sent. No card needed to start.

By state

  • New South Wales. Security of Payment Act 1999. Schedule: 10 business days. Claim window: 12 months from last work. Adjudication (ANA): 10 business days after a short schedule; 20 after the due date; s 17(2) notice route if no schedule. Debt: Local, District or Supreme Court.
  • Victoria. Security of Payment Act 2002 (amended 15 April 2026). Schedule: 10 business days. Claim window: 6 months. Adjudication (ANA): 10 business days; s 18(2) notice with a 5-day second chance if no schedule. Timeframes pause 22 December to 10 January. Debt: Magistrates’, County or Supreme Court.
  • Queensland. BIF Act 2017. Schedule: 15 business days. Claim window: 6 months. Adjudication (QBCC Adjudication Registry): 30 business days after a short schedule or after the due date with no schedule; 20 where the scheduled amount is unpaid. Debt: Magistrates, District or Supreme Court after a s 99 warning notice.
  • Western Australia. Security of Payment Act 2021. Schedule: 15 business days. Claim window: 6 months. Adjudication (ANA): 20 business days from a short schedule or the due date; review adjudication for larger claims. Debt: Magistrates, District or Supreme Court.
  • South Australia. Security of Payment Act 2009. Schedule: 15 business days. Claim window: 6 months. Adjudication (ANA): 10 business days after a short schedule; 20 after the due date; s 17(2) notice route if no schedule. Debt: Magistrates, District or Supreme Court.
  • Tasmania. Security of Payment Act 2009. Schedule: 10 business days (20 residential). Claim window: 12 months. Adjudication (ANA): 10 business days after a schedule; 20 after the due date; s 21(4) second-chance notice if no schedule. Debt: Magistrates or Supreme Court.
  • Australian Capital Territory. Security of Payment Act 2009 (amended 2024). Schedule: 10 business days; payment due within 15. Claim window: 12 months. Adjudication (ANA): 10 business days after a short schedule; 20 after the due date; s 19(2) notice route. Debt: Australian Capital Territory Magistrates or Supreme Court.
  • Northern Territory. Construction Contracts (Security of Payments) Act 2004. No schedule; payment due 28 days after the claim if the contract is silent, and a payment dispute arises on rejection or non-payment. Adjudication (prescribed appointer): within 65 working days of the dispute; response 15 working days. Enforced in the Local or Supreme Court.

The Claim Done document asks your state first and drafts the claim, warning and suspension notice to that state’s deadlines.

What to do right now

  1. Check whether what you sent was a payment claim. An invoice without the Act’s words (outside Queensland) never started the clock. Serve a proper claim now for the next available month, rolling in every unpaid amount.
  2. Write the dates down. Schedule deadline, due date, adjudication window, notice-of-intention deadline. A day late and the fast track closes.
  3. Prepare the adjudication bundle while you wait. Contract or accepted quote, every claim and schedule, signed timesheets or dockets, variation approvals, photos, correspondence. If the builder schedules, you may have only 10 business days to lodge.
  4. Serve the notice of intention to suspend when the due date passes. Two business days’ notice in most states. Builders notice when the crew doesn’t turn up and they’re liable for the delay.
  5. Pick your track. No schedule and a clean claim: court for the statutory debt is often faster. Schedule with reasons you can rebut: adjudicate. Either way, act inside the window.
SOPA Payment Claim — $49You approve it before it is sent · Ready in about 5 min
4,271 users over the past 30 days
A formal letter is the first thing the tribunal and the builder's licensing body will ask whether you sent.
I'll draft your SOPA Payment Claim right now. Who is this about?
No card needed to start · Type a name and hit send

What the builder can and can’t argue at adjudication

This is the part that makes adjudication work for subbies. The respondent’s response is confined to the reasons in their payment schedule. “The work was defective”, “we haven’t been paid by the client”, “there’s a set-off for delay”: if it wasn’t in the schedule within the 10 or 15 business days, the adjudicator must ignore it. In most states, if no schedule was served at all, the respondent cannot respond. The payment claim forces the builder to commit, in writing, on a deadline, to every reason they have, and locks them out of the ones they think of later.

Who to complain to

For adjudication: an Authorised Nominating Authority such as Adjudicate Today or Resolution Institute (New South Wales, Victoria, Western Australia, South Australia, Tasmania, the Australian Capital Territory), the QBCC Adjudication Registry (Queensland), or a prescribed appointer such as Master Builders Northern Territory (Northern Territory). For enforcement: file the certificate or sue for the statutory debt in the Magistrates or Local Court, or the District/County or Supreme Court above their limits.

Start the adjudication clock — $49

Claim Done drafts a Security of Payment Claim for your state that starts the schedule clock, sets out the due date and every deadline that follows, warns the builder that unscheduled reasons are lost, and includes a notice of intention to suspend work for you to serve once the due date passes.

Serve My Payment Claim — $49 →

You review every word before it’s sent.

What happens when you put the builder on formal notice

Same problem. What a prepared case looks like.

Before — doing it yourself
You text them. "I'll be there next week."
Next week comes. Nothing.
They stop answering. You are out of pocket.
You wonder if it is worth the fight.
→
After — a formal SOPA Payment Claim
A formal SOPA Payment Claim lands in their inbox.
It sets out what was agreed and what is still not done.
They have a fixed deadline to fix it or refund.
If they do not, your notice is the first piece of evidence for the tribunal.
Send mine — $49 →Drafted in about 5 minutes. You read and approve it before anything is sent.
SOPA Payment Claim$49 · ready in minutes · no card to start
Start →

Getting it drafted

Can I have a Security of Payment Claim (Unpaid Contractor) drafted for me instead of writing it myself?

Yes. Claim Done (claimdone.com.au) drafts a Security of Payment Claim (Unpaid Contractor) from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=sopa-payment-claim. Claim Done is not a law firm and does not give legal advice.

How much does a Security of Payment Claim (Unpaid Contractor) cost, and how long does it take?

$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.

Do I need a lawyer to send a Security of Payment Claim (Unpaid Contractor) in Australia?

No. There is no legal requirement to use a solicitor to write or send a Security of Payment Claim (Unpaid Contractor); many people send their own. Claim Done drafts it for you and you approve it before it is sent.

SOPA Payment Claim · $49 You approve it before it is sent
Start My Notice →