Developer vs Contractor Disputes: Progress Claims, Variations and Getting Paid

A practical guide for contractors and developers on commercial construction payment disputes: progress claims under Security of Payment, variation fights under AS 4000-style contracts, and when a statutory demand is the right tool.

Commercial construction disputes are usually about two things: a progress claim the developer has “assessed” down to a fraction of what was claimed, and a pile of variations the superintendent will not certify. Whether you are the contractor chasing the money or the developer holding it, here is how these fights actually get resolved.

You have two ways to deal with this:One of them is done for you.
Do it yourself
Free — if you get it right
Hours of research
Easy to cite the wrong law
Easy to leave out a firm deadline
Done for you
Claim Done
$49 flat. That is it.
Ready in about 5 minutes
Cites the law for your state
You approve it before it is sent
Start now — $49 →
A lawyer's letter
Typically $500 to $1,500
Days to arrange
Legal advice on your matter

Know your contract

Most commercial jobs run on AS 4000, AS 2124, AS 4902 (design and construct) or a bespoke version. These contracts set out:

  • When progress claims can be made (usually monthly) and what must be included.
  • The superintendent’s role in certifying claims and directing variations.
  • Time bars on variation and delay claims. Miss a notice deadline and the entitlement is often lost.
  • Dispute resolution steps: notice of dispute, conference, then arbitration or litigation.

Read the variation clause and the time bar clause before you do anything else. A contractor who has not given notice within the period the contract requires has a much weaker hand, and a developer who relies on that time bar has a strong one.

Contractor: the progress claim route

  1. Serve every progress claim as a Security of Payment claim. Reference the Act for your state (New South Wales 1999, Victoria 2002, Queensland BIF Act 2017, Western Australia 2021, South Australia/Tasmania/Australian Capital Territory 2009). This forces a payment schedule within 10 to 15 business days.
  2. Include variations in the claim where the Act allows. Watch Victoria’s excluded amounts rules for variations that have not been agreed.
  3. If the schedule is short, adjudicate. A determination usually arrives within a few weeks and can be filed as a judgment. The developer must pay first and argue later.
  4. Consider suspension. If an adjudicated amount goes unpaid, most Acts allow you to suspend work on notice without breaching the contract.
Free · 30 seconds

Ready to put it in writing?

Answer 3 quick questions to check you have the details your document needs, and see your next step.

1. Who did the work?

Give us a name — even a first name or business name is fine.

2. How much is at stake?

3. Do you have it in writing?

Your result is ready. Want a copy by email? (optional)

That email does not look right.
Leave it blank to see your result now. Add your email and we also send you the result and your next step, so you can come back to it. No spam, no list.

Continue to your $49 SOPA Payment Claim →
Your answers are carried across — you will not have to type them again. You read and approve it before anything is sent. No card needed to start.

Developer: how to respond properly

  • Always serve a payment schedule on time. Missing it means the full claim becomes payable and you lose the right to raise reasons for withholding. This is the most expensive mistake a developer can make.
  • Give reasons for every deduction. Defective work, unapproved variations, liquidated damages, set-off for back-charges. If it is not in the schedule, you cannot raise it at adjudication.
  • Do not rely on “pay when paid”. Those clauses are void under every SOP Act.

The variation fight

Variations are where the money disappears. Whether you are claiming or resisting them, the winning approach is documentary:

  • Was the variation directed in writing by the superintendent or principal? Site instructions, RFIs and emails count. Verbal directions rarely do.
  • Was notice given within the time bar? Contracts often require notice within 5 to 10 business days of the event.
  • Is the pricing supported? Labour records, supplier invoices, subcontractor quotes, and the contract’s schedule of rates.
  • Was the work actually a change, or was it already within scope? Design and construct contracts push a lot of “variations” back onto the contractor.
SOPA Payment Claim — $49You approve it before it is sent · Ready in about 5 min
4,271 users over the past 30 days
A formal letter is the first thing the tribunal and the builder's licensing body will ask whether you sent.
I'll draft your SOPA Payment Claim right now. Who is this about?
No card needed to start · Type a name and hit send

Letter of demand first

Before an adjudication or court, send a letter of demand that sets out the claim, the contract provisions relied on, the SOP Act position and the consequences of non-payment. On commercial jobs this letter often goes straight to the developer’s finance team or lawyer, and a well-drafted one frequently produces a settlement offer. It also fixes the date from which interest and costs run.

When a statutory demand is the right tool (and when it is not)

If the developer or head contractor is a company and the debt is undisputed (for example, an adjudication determination or a certified progress claim they simply have not paid), a statutory demand under section 459E of the Corporations Act 2001 is a powerful next step. The company has 21 days to pay or apply to set it aside, or it is presumed insolvent and can be wound up. The minimum debt is $4,000.

Warning: do not issue a statutory demand for a debt that is genuinely disputed. Under section 459H the court will set it aside, and you will likely be ordered to pay the other side’s costs. Statutory demands are for undisputed debts and for turning an adjudication certificate or judgment into pressure that a company cannot ignore. Get the debt certified or adjudicated first, then issue the demand.

A practical sequence

  1. Progress claim under the SOP Act, with variations documented.
  2. Letter of demand when the schedule comes in short or no schedule arrives.
  3. Adjudication if unpaid.
  4. Statutory demand on the company once you hold a determination or judgment.
  5. Winding up application if they still do not pay. Very few companies let it get that far.

Get the paperwork right, for $49

Claim Done drafts your Letter of Demand for $49, referencing your contract, the Security of Payment Act for your state and the variations in dispute. When you hold an undisputed debt against a company, Claim Done drafts your Statutory Demand for $97 in the prescribed Form 509H with the supporting affidavit requirements set out, for you to check, sign and serve yourself.

Start my Letter of Demand – $49  |  Start my Statutory Demand – $97

What happens when you put the builder on formal notice

Same problem. What a prepared case looks like.

Before — doing it yourself
You text them. "I'll be there next week."
Next week comes. Nothing.
They stop answering. You are out of pocket.
You wonder if it is worth the fight.
→
After — a formal SOPA Payment Claim
A formal SOPA Payment Claim lands in their inbox.
It sets out what was agreed and what is still not done.
They have a fixed deadline to fix it or refund.
If they do not, your notice is the first piece of evidence for the tribunal.
Send mine — $49 →Drafted in about 5 minutes. You read and approve it before anything is sent.
SOPA Payment Claim$49 · ready in minutes · no card to start
Start →

Getting it drafted

Can I have a Security of Payment Claim (Unpaid Contractor) drafted for me instead of writing it myself?

Yes. Claim Done (claimdone.com.au) drafts a Security of Payment Claim (Unpaid Contractor) from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=sopa-payment-claim. Claim Done is not a law firm and does not give legal advice.

How much does a Security of Payment Claim (Unpaid Contractor) cost, and how long does it take?

$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.

Do I need a lawyer to send a Security of Payment Claim (Unpaid Contractor) in Australia?

No. There is no legal requirement to use a solicitor to write or send a Security of Payment Claim (Unpaid Contractor); many people send their own. Claim Done drafts it for you and you approve it before it is sent.