The Tasmanian Civil and Administrative Tribunal — known as TASCAT — is Tasmania’s main forum for resolving civil disputes between consumers and tradespeople without the cost and formality of a court. If a builder, plumber, electrician, painter or other tradesperson has left your job unfinished, done it poorly, or caused damage in the process, TASCAT has the power to hear your complaint and make binding orders.
How TASCAT decides a defective-work dispute
TASCAT looks at whether the work met the standard a reasonable consumer was entitled to expect. In practice, the tribunal considers several key questions:
- Was there a contract — written or verbal — and what did it promise?
- Did the tradesperson carry out the work in a proper and workmanlike manner using suitable materials?
- Was the work completed within a reasonable time?
- Did the consumer pay, or were payments withheld for a genuine reason?
- What loss or cost has the defective or incomplete work actually caused?
Tasmania’s consumer-protection and fair-trading laws imply certain guarantees into service contracts. Even if nothing was written down, a tradesperson is generally expected to work with due care and skill, and to complete the job within the time agreed or within a reasonable time. TASCAT applies those standards when weighing up the evidence from both sides.
Orders TASCAT can make
If TASCAT finds in your favour, it has a range of remedies available. The tribunal may order the tradesperson to:
- Refund some or all of the money you paid
- Pay you a sum to cover the reasonable cost of having someone else fix or complete the work
- Return to the property and rectify specific defects within a set timeframe
- Compensate you for consequential loss caused by the defective work — for example, damage to your home or belongings
TASCAT aims to put you back in the position you would have been in had the work been done properly. It will not award a windfall beyond your actual loss.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who did the work?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
How to apply to TASCAT
The application process is designed to be accessible to everyday consumers. In general terms:
- Gather your evidence before you apply (see below).
- Attempt to resolve the dispute directly with the tradesperson first — a formal letter of demand can demonstrate you tried.
- Download and complete the correct application form from the TASCAT website. Current forms and filing fees are listed on the tribunal’s own site, as these details change from time to time.
- Lodge your application online, by post or in person at a TASCAT registry.
- TASCAT will notify the tradesperson and set a hearing or conciliation date.
Many disputes are resolved at an early conciliation stage without a formal hearing. If conciliation fails, the matter proceeds to a hearing where a TASCAT member makes a final decision.
Evidence that strengthens your case
The stronger your evidence, the clearer your claim. Useful material includes:
- Your original contract, quote or written agreement
- Text messages, emails or notes of verbal conversations with the tradesperson
- Photographs and video of the defective or unfinished work
- Receipts or invoices showing what you paid
- A written quote or invoice from a second tradesperson showing what it will cost to fix the work
- An independent expert or building inspector’s report describing the defects
- A clear timeline showing when work was due, when it stopped, and what you did to raise the problem
TASCAT members are experienced in weighing practical, real-world evidence. You do not need a lawyer, but organised, clear documentation makes a significant difference.
How Claim Done helps
Before you lodge at TASCAT, sending a professionally drafted letter of demand often prompts a tradesperson to settle without a tribunal hearing at all. Claim Done prepares a clear, firm demand letter tailored to your situation — setting out the defects, the amount sought and a deadline for response. That letter also becomes part of your evidence file if the matter does proceed to TASCAT, showing the tribunal that you gave the tradesperson a fair opportunity to fix things first.
What happens when you put the builder on formal notice
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Letter of Demand drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Letter of Demand from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=letter-of-demand. Claim Done is not a law firm and does not give legal advice.
How much does a Letter of Demand cost, and how long does it take?
$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. Email delivery is free; registered post is $29 extra. It covers every Australian state and territory.
Do I need a lawyer to send a Letter of Demand in Australia?
No. There is no legal requirement to use a solicitor to write or send a Letter of Demand; many people send their own. Claim Done drafts it for you and you approve it before it is sent.
What does Claim Done do that a free Letter of Demand template doesn't?
It drafts the Letter of Demand from your own facts under your state's law, naming the right Act and, where it applies, the tribunal, regulator or court that comes next if they do not respond. Nothing is sent until you approve it. Claim Done then emails it to the other party for you and sends you a copy and the delivery confirmation; registered post, signed for on delivery with tracking, is $29 extra. The key dates in the letter are listed on your dashboard.