If a builder, contractor or tradesperson has left your Tasmanian home with defective, incomplete or substandard work, the Tasmanian Civil and Administrative Tribunal (TASCAT) is the main forum for resolving that dispute without going to court. TASCAT handles civil building and construction matters and can make binding orders against builders and contractors.
How TASCAT Decides Building Disputes
When TASCAT considers a building defect claim it looks at whether the work met the standard reasonably expected under the contract and under the consumer guarantees that apply to building work in Tasmania. Key questions the tribunal examines include:
- Whether the work was carried out in a proper and workmanlike manner
- Whether materials used were fit for their intended purpose
- Whether the work conformed to the plans, specifications and any agreed scope
- Whether the builder was given a reasonable opportunity to fix the defects before the dispute was lodged
- The extent of any financial loss, additional costs or diminution in property value caused by the defective work
TASCAT may appoint or receive evidence from a building expert to assist it in understanding technical issues, and it applies practical, common-sense reasoning to resolve disputes fairly between homeowners and builders.
Orders TASCAT Can Make
TASCAT has broad powers in building disputes. Depending on what the evidence shows, the tribunal may order:
- Rectification — requiring the builder or contractor to return and fix the defective or incomplete work
- Compensation — awarding the homeowner a sum of money to cover the reasonable cost of having the work fixed by another contractor
- Reduction in the contract price to reflect work that was not completed or not completed to the required standard
- Reimbursement of costs directly caused by the defective work, such as temporary accommodation or consequential damage to the property
The tribunal aims to put the homeowner in the position they would have been in had the work been done properly in the first place.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who is this about?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
How to Apply to TASCAT
Before applying, it is worth writing formally to the builder to identify the defects, state what you want done and give a reasonable deadline to respond. This shows the tribunal you attempted to resolve the matter first.
- Gather your contract, invoices and any written communications with the builder.
- Obtain at least one independent builder’s or inspector’s report describing the defects and the estimated cost of rectification.
- Complete the relevant application form available on the TASCAT website. Current forms, filing fees and lodgement instructions are published directly on the tribunal’s own website, as fees and procedures can change.
- Lodge your application and pay the applicable filing fee. TASCAT will then notify the other party and schedule a hearing or conciliation.
Many TASCAT building matters proceed through a preliminary conference or conciliation before a full hearing, giving both parties an early chance to settle.
Evidence That Helps Your Case
Strong evidence significantly improves your prospects at TASCAT. The most useful material includes:
- A signed, written contract and any variation agreements
- Photographs and videos of the defective work, taken as soon as possible
- An independent building inspection report that identifies each defect, links it to the builder’s work and estimates the rectification cost
- All written correspondence with the builder, including emails, text messages and letters
- Receipts or quotes for any remedial work already undertaken or obtained
- A clear, itemised schedule of defects you prepare yourself, cross-referenced to your inspection report
How Claim Done Helps
A well-drafted formal letter of demand addressed to the builder — setting out each defect, the evidence supporting your claim and the amount or remedy you are seeking — demonstrates to TASCAT that you approached the dispute seriously and professionally. Claim Done prepares that letter for a flat fee, using language that mirrors the standard a tribunal expects, so you arrive at TASCAT with a clear paper trail and a document that can be tendered as part of your evidence.
What happens when you put it in writing — properly
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Defects Notice to Your Builder drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Defects Notice to Your Builder from the answers you give about your situation for a flat $79 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=home-building-defects-claim. Claim Done is not a law firm and does not give legal advice.
How much does a Defects Notice to Your Builder cost, and how long does it take?
$79 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. Email delivery is free; registered post is $29 extra. It covers every Australian state and territory.
Do I need a lawyer to send a Defects Notice to Your Builder in Australia?
No. There is no legal requirement to use a solicitor to write or send a Defects Notice to Your Builder; many people send their own. Claim Done drafts it for you and you approve it before it is sent.
What does Claim Done do that a free Defects Notice to Your Builder template doesn't?
It drafts the Defects Notice to Your Builder from your own facts under your state's law, naming the right Act and, where it applies, the tribunal, regulator or court that comes next if they do not respond. Nothing is sent until you approve it. Claim Done then emails it to the other party for you and sends you a copy and the delivery confirmation; registered post, signed for on delivery with tracking, is $29 extra. The key dates in the letter are listed on your dashboard.