If a builder has left your renovation incomplete, done defective work, or breached the contract, the Victorian Civil and Administrative Tribunal (VCAT) Building and Property List is where disputes are resolved. Unlike general civil claims, domestic building cases follow a structured process with mandatory conciliation before hearing.
What qualifies for the Building and Property List
VCAT’s Building and Property List hears disputes under domestic building contracts. The most common claims are:
- Defective work — poor workmanship, non-compliant building, work not to Australian Standards
- Incomplete work — builder walked off site, contract terminated, project abandoned
- Variations not authorised — contractor charged for work you did not approve
- Delay claims — liquidated damages or loss caused by unreasonable delay
- Payment disputes — final invoice disputes, retention withheld, progress claims
- Breach of statutory warranties — warranties implied by Victorian building legislation (workmanlike manner, suitable materials, compliance with laws)
Before you apply: for most domestic building disputes, VCAT can only hear the claim after the Building and Plumbing Commission’s dispute resolution service has dealt with it and issued a certificate of conciliation (Domestic Building Contracts Act 1995 (Vic) s 56).
Time limit: You typically have 10 years from the date the building work was completed (or should have been completed). For defects that appear later, the time runs from when the defect became apparent, but still within the 10-year long-stop.
Step 1: Pre-application requirements
Before filing at VCAT, you must attempt to resolve the dispute directly with the builder. This is not optional.
What you must do:
- Send a written notice outlining the defects, breach, or claim
- Allow a reasonable time for the builder to respond or remedy (typically 14-28 days)
- Keep records of all correspondence, photos, quotes for rectification, and any response
If the builder ignores you, refuses to fix the work, or disputes liability, you can proceed to VCAT. The tribunal will ask whether you attempted resolution first.
Ready to put it in writing?
Answer 3 quick questions to check you have the details your document needs, and see your next step.
1. Who did the work?
2. How much is at stake?
3. Do you have it in writing?
Your result is ready. Want a copy by email? (optional)
Step 2: Filing your VCAT application
You file online or by post using the Domestic Building application form (available on the VCAT website).
What you need to include:
- Statement of claim — describe the work done, what went wrong, what you are claiming, and the amount
- Contract and variations — the signed building contract, any variation orders, quotes, invoices
- Evidence of defects — photos, videos, independent reports (engineer, building inspector, quantity surveyor)
- Correspondence — your demand letter, the builder’s response (if any)
- Quotes for rectification — at least two quotes from licensed builders to fix the defects
- Proof of payment — bank statements, receipts showing what you paid
Filing fee: The fee depends on the claim amount; check VCAT’s current fees before you apply.
Service: Follow VCAT’s instructions for giving the builder a copy of your application.
Step 3: Mandatory conciliation conference
VCAT will usually schedule a compulsory conference (conciliation). Both parties must attend.
What happens at conciliation:
- A VCAT conciliator facilitates negotiation
- You and the builder present your positions informally
- The conciliator helps identify common ground and settlement options
- If you settle, VCAT issues consent orders — legally binding and enforceable
- If you do not settle, the matter proceeds to hearing
What to bring:
- All your evidence (photos, reports, quotes, contract)
- A clear understanding of what you want (money, rectification, both)
- Authority to settle — if you are not the sole owner, bring written authority from co-owners
Many domestic building disputes settle at conciliation. Settlement avoids the cost, delay, and uncertainty of a hearing.
Step 4: Preparing for the VCAT hearing
If conciliation fails, VCAT schedules a hearing. This is a formal tribunal process where both sides present evidence and the tribunal member makes a binding decision.
Evidence you need:
- Expert reports — building inspector, engineer, or quantity surveyor report detailing defects, cause, and rectification cost
- Photographic evidence — date-stamped photos showing defects, incomplete work, damage
- Rectification quotes — at least two quotes from licensed builders, itemised and detailed
- Contract documents — the signed contract, variations, specifications, plans
- Correspondence — all emails, letters, text messages between you and the builder
- Payment records — invoices, receipts, bank statements proving what you paid
- Witness statements — if relevant, statements from tradespeople, neighbours, or others who saw the work
Expert evidence is critical. VCAT expects independent professional opinion on defects and costs. A report from a qualified building inspector or engineer carries far more weight than your own assessment.
Step 5: The VCAT hearing
The hearing is less formal than court, but still structured. The tribunal member hears both sides and makes a decision.
Hearing process:
- Opening statements — each party outlines their case (5-10 minutes)
- Applicant’s evidence — you present your evidence, call witnesses, tender reports
- Cross-examination — the builder (or their representative) can question your witnesses
- Respondent’s evidence — the builder presents their case and witnesses
- Cross-examination — you can question the builder’s witnesses
- Closing submissions — each party summarises their case
- Decision — the tribunal member may decide on the day, or reserve their decision and issue written reasons later
What VCAT can order:
- Payment of damages (cost to rectify defects, loss suffered)
- Specific performance (order the builder to complete or fix the work)
- Refund of money paid for work not done
- Costs (limited — typically each party pays their own costs unless there was unreasonable conduct)
Common mistakes to avoid
Filing too early: You must give the builder a reasonable opportunity to respond to your complaint before filing. If you file immediately, VCAT may adjourn and order you to attempt resolution first.
No expert evidence: Claims for defective work almost always require an independent expert report. Without one, VCAT has no objective basis to assess your claim.
Poor documentation: If you cannot prove what was agreed, what you paid, or what defects exist, your claim will fail. Keep everything in writing.
Overstating the claim: Claiming $50,000 when rectification quotes total $20,000 damages your credibility. Claim what you can prove.
Ignoring conciliation: Conciliation is your best chance to settle without the cost and delay of a hearing. Come prepared to negotiate.
Final steps after the VCAT decision
If you win, VCAT issues an order. The builder must comply within the time specified (typically 28 days for payment).
If the builder does not pay: You can enforce the VCAT order in the Magistrates’ Court as if it were a court judgment. This allows you to use enforcement methods like garnishee orders, instalment orders, or examination summons.
If you lose: You can appeal to the Supreme Court, but only on a question of law (not on factual findings). Appeals are expensive and rarely succeed.
If the builder is insolvent: You may be able to claim under the builder’s domestic building insurance (required for contracts over $16,000 in Victoria). Contact the Building and Plumbing Commission for advice.
How Claim Done helps with VCAT domestic building disputes
Claim Done drafts your VCAT application and a witness statement in about 5 minutes. You tell us about your contract, photos, quotes, and correspondence. Our Programmatic Algorithms draft your statement of claim and prepare the application.
We also generate the demand letter you need to send before filing — citing the applicable Victorian building legislation and the statutory warranties.
What you get:
- Your VCAT application
- Statement of claim citing the applicable law and your evidence
- A witness statement
- Demand letter sent to the builder before filing (if required)
Flat fee. No subscription. Done in about 5 minutes.
Claim Done does not give legal advice.
Start your VCAT application now at claimdone.com.au/services/tribunal-application — tell us what evidence you have and get your application drafted in about 5 minutes, then lodge it yourself.
Frequently Asked Questions
Do I need a lawyer for a VCAT domestic building dispute?
No. VCAT is designed for self-representation, and most claims under $50,000 are handled without lawyers.
How long does a VCAT domestic building case take?
VCAT gives an average of about 52 weeks from applying to a hearing in building and construction cases, and says it may be earlier or later depending on what you are applying about.
Can I claim for defects that appeared after the builder finished?
Yes. You can claim for latent defects (defects that were not visible at the time of completion) within 10 years of completion. The time limit runs from when the defect became apparent, but still within the 10-year long-stop period.
What if the builder has gone out of business?
If the builder is insolvent or deregistered, you may be able to claim under their domestic building insurance (required for contracts over $16,000 in Victoria). Contact the Building and Plumbing Commission about a claim on the domestic building insurance policy.
Can VCAT order the builder to fix the defects, or only pay damages?
VCAT can order specific performance (requiring the builder to complete or rectify the work), but this is rare. Most orders are for damages (the cost to rectify the defects). If the builder is unlikely to comply, a damages order is more practical and enforceable.
Need this document prepared for you?
Claim Done generates professional legal documents from your evidence in about 5 minutes. Flat fee. No subscription.
What happens when you put the builder on formal notice
Same problem. What a prepared case looks like.
Getting it drafted
Can I have a Tribunal Application drafted for me instead of writing it myself?
Yes. Claim Done (claimdone.com.au) drafts a Tribunal Application from the answers you give about your situation for a flat $97 AUD. You read and confirm the draft, then the final PDF is emailed to you. Start at claimdone.com.au/begin/?service=tribunal-application. Claim Done is not a law firm and does not give legal advice.
How much does a Tribunal Application cost, and how long does it take?
$97 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. It covers every Australian state and territory.
Does Claim Done lodge the application with the tribunal or court?
No. Claim Done drafts the documents; you lodge them yourself and pay the tribunal's or court's own filing fee directly to it. The draft names the right tribunal or court and Act for your state.
What does Claim Done do that a free tribunal application template doesn't?
It sets out your claim to match your state's tribunal or court application (for a New South Wales debt, a Local Court statement of claim) under the right Act, with a witness statement drafted from your account (in New South Wales, the outline NCAT requires) and the documents you mention referred to as numbered exhibits. You read every word, change it or ask for a redraft (two are included), then lodge it yourself.