You completed the works. You submitted the progress claim. The head contractor accepted delivery, used your work to invoice the principal, and then either silently let your invoice age or began the slow drip of “we are waiting on the principal” excuses. Your suppliers, your crew and your bank do not extend the same generosity you have been forced to extend upstream.
Subcontractors in Australia have two parallel and powerful sets of rights — contractual debt-recovery rights, and statutory rights under each state’s Security of Payment legislation. Used together, they convert a stalled head contractor into a quick payer faster than most subbies expect.
Why the “we have not been paid” line does not stand up
The head contractor’s relationship with the principal is irrelevant to your right to be paid. Your contract is with the head contractor. The Building and Construction Industry Security of Payment legislation in your state (NSW 1999, Vic 2002, Qld 2017, WA 2021, SA 2009 and equivalents) gives you a statutory right to a progress payment for work done, regardless of what is happening upstream. “Pay-when-paid” clauses are unenforceable across most of Australia.
The legal step that gets payment moving
A Letter of Demand is the contractual first step — it formalises the debt, attaches updated interest, and signals court action. In parallel, where the work falls under construction-industry payment legislation, you can issue a payment claim that triggers the statutory regime. The statutory route is fast, cheap and carries an adjudication outcome that is enforceable as a court judgment.
What Claim Done delivers
- Subcontract, scope and progress claim history captured precisely
- Citation of the Security of Payment Act in your state where applicable
- Quantified debt with statutory interest
- Clear 14-day deadline and named escalation path
- Drafted and sent on professional letterhead, flat $79
Common head contractor pushbacks and why they fail
- “Pay-when-paid.” Unenforceable in NSW, Vic, Qld and most other jurisdictions for SOPA-covered work.
- “The principal is in dispute.” Their dispute is their problem. Your right to payment for work done is independent.
- “There are defects.” Defects must be properly notified and quantified; bare assertions do not justify withholding payment for accepted work.
- “You were late.” Delay claims must be properly raised under the contract; informal complaints rarely defeat a payment claim.
Next escalation if the demand is ignored
Two parallel tracks. The contractual track moves through Final Demand ($79) and into the small claims tribunal, Magistrates Court, or Statutory Demand under section 459E for corporate head contractors over $4,000. The SOPA track moves through a payment claim, payment schedule (or absence of one), and adjudication — typically resolved inside 30 to 45 days with an enforceable adjudication certificate. Subcontractors who run both tracks in parallel get paid materially faster than those who choose one. A formal Letter of Demand sets the stage for either route.