02 8880 1347
← Legal Guides Published · Updated

Contractor Wants More Money After the Job: Do You Have to Pay?

A contractor finishing a job then demanding more money is frustrating and common. Whether you're legally required to pay depends on your contract, what was agreed, and whether the extra work was authorised.

Start your Legal Response — $49 →Drafted from your answers in minutes · you review it before anything is sent

Topics: building disputes, contract variations, contractor disputes, payment disputes, scope creep

You hired a contractor. They quoted a price. You agreed. The job is done — and now they’re demanding more money.

This happens thousands of times across Australia every year: tradies, builders, consultants, and freelancers finishing work then claiming the agreed price doesn’t cover what they actually did. Sometimes the claim is legitimate. Often it’s not.

You have two ways to deal with this:One of them is done for you.
Do it yourself
Free — if you get it right
Hours of research
Easy to cite the wrong law
Easy to leave out a firm deadline
Done for you
Claim Done
$49 flat. That is it.
Ready in about 5 minutes
Cites the law for your state
You approve it before it is sent
Start now — $49 →
A lawyer's letter
Typically $500 to $1,500
Days to arrange
Legal advice on your matter

What the Law Says About Agreed Prices

Under Australian contract law, an agreement is binding once both parties accept the terms. If you agreed to pay $5,000 for a bathroom renovation and the contractor accepted that price, that’s the contract. The contractor cannot unilaterally change the price after the fact simply because the job took longer or cost them more than expected.

You are only required to pay what was agreed in the contract, unless:

  • You authorised additional work in writing
  • The contract includes a valid variation clause that was properly followed
  • Unforeseen circumstances arose that fundamentally changed the scope (rare)
  • You agreed verbally to extras and the contractor can prove it

If none of these apply, the demand has no legal basis.

When a Contractor’s Claim Is Valid

Not every post-job demand is a shakedown. There are legitimate scenarios where you may owe more than the original quote.

Authorised Variations

If you asked the contractor to do additional work during the job — install an extra power point, use higher-grade materials, extend the deck by two metres — and you agreed to pay extra for it, that’s a valid variation. The contractor is entitled to payment even if nothing was put in writing, though proving a verbal agreement is harder.

What makes a variation enforceable:

  • You requested work outside the original scope
  • The contractor informed you there would be an additional charge
  • You agreed to proceed knowing the cost
  • The work was actually completed

If the contractor can demonstrate these elements through texts, emails, or witness testimony, the extra charge stands.

Contract Variation Clauses

Many written contracts include a variation clause allowing the contractor to charge more if certain conditions arise. Common examples:

  • “Additional costs due to unforeseen site conditions will be charged at $X per hour”
  • “Variations must be approved in writing by the client before work commences”
  • “The contractor may adjust the price if materials costs increase by more than 10%”

The key question: Did the contractor follow the process set out in the contract? If the clause requires written approval and they proceeded without it, the variation is typically not enforceable.

Unforeseen Circumstances (Rarely Applies)

Australian courts recognise that truly unforeseen circumstances can sometimes justify a price adjustment — but the threshold is high. Discovering asbestos during a renovation, finding the ground composition completely different from what was visible, or encountering structural damage that makes the original scope impossible are examples.

What does not qualify:

  • The job took longer than expected
  • Materials cost more than the contractor anticipated
  • The contractor underquoted to win the job
  • The work was harder than they thought

These are commercial risks the contractor bears. Getting the quote wrong does not create a legal right to charge you more.

Free · 30 seconds

Ready to put it in writing?

Answer 3 quick questions to check you have the details your document needs, and see your next step.

1. Who is the claim or demand from?

Give us a name — even a first name or business name is fine.

2. How much are they claiming?

3. Do you have it in writing?

Your result is ready. Want a copy by email? (optional)

That email does not look right.
Leave it blank to see your result now. Add your email and we also send you the result and your next step, so you can come back to it. No spam, no list.

Continue to your $49 Legal Response →
Your answers are carried across — you will not have to type them again. You read and approve it before anything is sent. No card needed to start.

When You Can Refuse to Pay

If the contractor’s demand does not fall into one of the valid categories above, you are entitled to refuse.

No Written Variation

If your contract required variations to be approved in writing and the contractor did extra work without getting your signature, you are not obliged to pay for it. The contractor took a commercial risk by proceeding without authorisation.

Scope Creep Without Agreement

Scope creep — where a contractor gradually expands the work beyond what was agreed — does not create a payment obligation unless you explicitly agreed to each addition. If the contractor decided on their own initiative to “upgrade” materials, add features, or redo work to a higher standard than specified, that’s their choice, not your debt.

Poor Quality or Incomplete Work

If the contractor is demanding more money while the original job remains incomplete or defective, you have a strong basis to refuse. Australian Consumer Law requires services to be provided with due care and skill. A contractor who hasn’t met that standard has no grounds to demand extra payment.

Verbal Agreements You Dispute

If the contractor claims you verbally agreed to extras and you have no memory of that conversation, it’s their burden to prove the agreement existed. Absent evidence, a disputed verbal agreement is unlikely to be enforceable.

What to Do When a Contractor Demands More Money

Review the Contract

Pull out the written agreement (if one exists) and read it carefully. Look for:

  • The total agreed price
  • What work was included in that price
  • Any variation clauses
  • Any provisions about additional costs

If there’s no written contract, reconstruct what was agreed by reviewing quotes, emails, text messages, and any other correspondence.

Identify What Was Authorised

Go through your communications with the contractor. Did you approve any additional work? Did you agree to any changes? If yes, what was the agreed price for those changes?

Be honest with yourself. If you asked for extras and agreed to pay more, the contractor’s claim may be valid even if you didn’t expect the final bill to be this high.

Request a Breakdown

If the contractor’s demand is vague (“I need another $3,000 for extras”), ask for an itemised breakdown showing:

  • What additional work was done
  • When you authorised it
  • What the agreed price was
  • Evidence of your approval (emails, texts, signed variation forms)

A legitimate claim will be supported by documentation. A contractor who cannot provide specifics is likely trying it on.

Respond in Writing

Do not ignore the demand. Send a clear written response setting out your position:

  • Acknowledge receipt of the demand
  • State what you agreed to pay and why
  • Identify any disputed items and explain why you dispute them
  • Offer to pay any amounts you genuinely owe
  • Refuse to pay amounts that were not authorised

Keep the tone professional and factual.

Negotiate if Appropriate

If there’s a genuine grey area — you did ask for some extras but the price seems inflated, or you agreed verbally but can’t recall the exact amount — consider negotiating a compromise. Paying a reasonable sum to resolve the dispute may be cheaper and faster than fighting it.

Legal Response — $49You approve it before it is sent · Ready in about 5 min
4,282 users over the past 30 days
Set out what you accept, what you dispute and what you propose, in one dated document.
I'll draft your Legal Response right now. Who is the claim or demand from?
No card needed to start · Type a name and hit send

What Happens If You Refuse to Pay

If you refuse to pay and the contractor believes they’re entitled to the money, they have several options.

Demand Letter

The contractor may send a formal letter of demand threatening legal action if you don’t pay. This is not a court order. It’s a negotiation tactic. You are not required to comply simply because a letter arrived.

Tribunal Claim

For amounts up to $10,000 (New South Wales, Victoria), $25,000 (Queensland, Western Australia, South Australia), or other state-specific limits, the contractor can file a claim in the relevant civil tribunal. You’ll receive a notice to appear and will need to present your defence.

Security of Payment Claim (Construction Only)

If the work falls under security of payment legislation in your state, the contractor may issue a payment claim and potentially suspend work or seek adjudication. This process is fast and technical — if you receive a payment claim under this regime, act immediately.

Debt Recovery or Court

For larger amounts, the contractor may engage a debt collector or file a claim in the District or Magistrates Court. Court proceedings are slower and more expensive, which often motivates both sides to settle.

How Claim Done Helps

If a contractor is demanding money you don’t believe you owe, Claim Done’s Legal Response service prepares a professionally formatted reply in about 5 minutes.

Upload the contractor’s demand, your contract, and any relevant communications. Claim Done’s Programmatic Algorithms analyse the claim, identify the legal weaknesses, and draft a response that:

  • Sets out what was actually agreed
  • Explains why the additional charge is not enforceable
  • Cites relevant contract principles and consumer protection provisions
  • Offers to pay any genuinely owed amounts (if applicable)
  • States your position clearly and confidently

The response is generated and ready to send for a flat fee of $49 — no lawyers, no hourly billing, no waiting weeks for a reply.

If the dispute escalates to tribunal, Claim Done’s Tribunal Response / Defence Pack drafts a response summary, a defence position statement, a chronology and an evidence list, so you can represent yourself.

Key Takeaways

You are only required to pay what was agreed. A contractor cannot unilaterally increase the price after the job is done simply because it cost them more than expected.

Variations must be authorised. If you didn’t approve additional work, you don’t owe for it — even if the contractor claims it was necessary.

Follow your contract. If the contract requires written approval for variations, verbal agreements may not be enforceable.

Respond in writing. Ignoring a demand doesn’t make it go away. A clear, documented response protects your position.

Negotiate where reasonable. If there’s genuine ambiguity, a compromise may be faster and cheaper than a tribunal hearing.

A contractor demanding more money after finishing a job doesn’t automatically have a valid claim. Review your contract, identify what was actually authorised, and respond with confidence. If you need a professionally drafted response fast, Claim Done's Legal Response service delivers in about 5 minutes for $49.

Frequently Asked Questions

Can a contractor charge more if the job took longer than expected?

No. If you agreed to a fixed price, the contractor cannot charge more simply because the work took longer than they anticipated. Time estimates are the contractor’s responsibility. You only owe extra if you authorised additional work outside the original scope.

What if I verbally agreed to extras but can't remember the price?

If you genuinely agreed to additional work but didn’t discuss price, the contractor may be entitled to a reasonable amount for that work. However, if you dispute that any agreement was made, the contractor must prove the verbal agreement existed — typically through text messages, emails, or witness evidence.

Do I have to pay if the contractor threatens to put a lien on my property?

Threatening a lien does not create a legal obligation to pay. In some states, contractors can register caveats or claims over property for unpaid building work, but this requires following specific legal processes. If you believe the demand is invalid, you can dispute it. Do not pay simply because of a threat.

What happens if I refuse to pay and the contractor takes me to tribunal?

You will receive a notice to attend a tribunal hearing. You’ll need to present your evidence showing what was agreed, why the additional charge was not authorised, and any defences you have. Claim Done’s Tribunal Response service can draft your response documents so you can represent yourself.

Can I withhold payment if the original work is defective?

Yes. If the contractor has not completed the work to an acceptable standard or the work is defective, you are entitled to withhold payment until the defects are rectified. Under Australian Consumer Law, services must be provided with due care and skill. A contractor demanding more money while the original job remains substandard has no legal basis for that demand.

Need this document prepared for you?

Claim Done generates professional legal documents from your evidence in about 5 minutes. Flat fee. No subscription.

Let’s Begin →

What changes when your answer is in writing

Same problem. What a prepared case looks like.

Before — doing it yourself
They call or write demanding payment.
You are not sure what to say, or what you would be admitting.
Their deadline gets closer.
Nothing you have said is on the record.
→
After — a formal Legal Response
Your Legal Response sets out what you accept and what you dispute.
It explains why, and what you propose.
It is dated, so there is a record of your position.
You read it first and can change the wording.
Start mine — $49 →Drafted in about 5 minutes. You read and approve it before anything is sent.
Legal Response$49 · ready in minutes · no card to start
Start →

Getting it drafted

Can I have a Legal Response drafted for me instead of writing it myself?

Yes. Claim Done (claimdone.com.au) drafts a Legal Response from the answers you give about your situation for a flat $49 AUD. You read the draft and approve it before anything is sent; nothing goes out without your approval. Start at claimdone.com.au/begin/?service=legal-response. Claim Done is not a law firm and does not give legal advice.

How much does a Legal Response cost, and how long does it take?

$49 AUD flat, shown before you pay, with no subscription. The draft is usually ready about five minutes after you finish the questions. Email delivery is free; registered post is $29 extra. It covers every Australian state and territory.

Do I need a lawyer to send a Legal Response in Australia?

No. There is no legal requirement to use a solicitor to write or send a Legal Response; many people send their own. Claim Done drafts it for you and you approve it before it is sent.

What does Claim Done do that a free Legal Response template doesn't?

It drafts the Legal Response from your own facts under your state's law, naming the right Act and, where it applies, the tribunal, regulator or court that comes next if they do not respond. Nothing is sent until you approve it. Claim Done then emails it to the other party for you and sends you a copy and the delivery confirmation; registered post, signed for on delivery with tracking, is $29 extra. The key dates in the letter are listed on your dashboard.

Legal Response · $49 You approve it before it is sent
Get Started →